[2021] KEHC 5319 (KLR)

[2021] KEHC 5319 (KLR)

The court found that the County Government of Kilifi breached the amended agreement by unilaterally terminating it without following the contractual dispute resolution and termination procedures. The defendant's reliance on conditions precedent to justify termination was rejected; the court held that satisfaction...

Source-derived case information.

Citation
[2021] KEHC 5319 (KLR)
Parties
Plaintiff: Raindrops Limited; Defendant: County Government of Kilifi
Court
High Court
Court Station
High Court at Malindi
Jurisdiction
Kenya
Case Number
Civil Suit 9 of 2015
Procedural Posture
Civil Suit / Judgment
Outcome
Judgment for the plaintiff in part; counterclaim dismissed; damages and further orders as specified.
Judges
DB Nyakundi
Legal Topics
Breach of Contract, Public Private Partnerships, Public Procurement, County Revenue Collection, Damages and Remedies, Contractual Termination
Source Language
en
Commercial and Corporate Land and Property Civil Procedure Breach of Contract Public Private Partnerships Public Procurement County Revenue Collection Damages and Remedies +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 6 Authorities cited 14 Party arguments 2 Amounts and remedies 6
Sign in to unlock

Parties

Raindrops Limited

Plaintiff

County Government of Kilifi

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether the defendant lawfully terminated the amended revenue collection agreement with the plaintiff.
  2. 2 Whether the parties fulfilled their respective obligations under the amended agreement.
  3. 3 Whether the amended agreement or its performance contravened the Constitution or the Public Finance Management Act and was void ab initio.

Ratio Decidendi

The court found that the County Government of Kilifi breached the amended agreement by unilaterally terminating it without following the contractual dispute resolution and termination procedures. The defendant's reliance on conditions precedent to justify termination was rejected; the court held that satisfaction with the form and content of the agreement did not extend to performance issues. The defendant further breached the agreement by failing to provide land, office space, and seconded staff, frustrating the plaintiff's ability to perform. The court held that the apportionment of revenue should be based on net income, not gross, and that both parties are liable for taxes as per law....

Court Disposition

Judgment for the plaintiff in part; counterclaim dismissed; damages and further orders as specified.

Orders

  • Chief Government Valuer to conduct valuation of plaintiff's infrastructure within 30 days and file report for further orders.
  • Auditor General to take accounts of all revenue collected and file report within 30 days.