[2017] KEHC 7428 (KLR)
The court found that both parties breached the original construction agreement: the plaintiff failed to complete the works within the stipulated time, and the defendant failed to make timely payments as requested. The evidence, including expert reports, photographs, and a site visit, established that the main...
Source-derived case information.
- Citation
- [2017] KEHC 7428 (KLR)
- Parties
- Plaintiff: Raiya Constructions Ltd; Defendant: Sun Sand Dunes Ltd
- Court
- High Court
- Court Station
- High Court at Malindi
- Jurisdiction
- Kenya
- Judgment Date
- 7 March 2017
- Case Number
- Civil Suit 179 of 2012
- Procedural Posture
- Civil Suit / Judgment
- Outcome
- Plaintiff's claim partly succeeds; defendant's counter-claim dismissed; each party to bear its own costs.
- Judges
- SJ Chitembwe
- Legal Topics
- Building Contracts, Contractual Breach, Construction Disputes, Damages Assessment, Novation, Retention Clauses
- Source Language
- english
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Raiya Constructions Ltd
Plaintiff
Sun Sand Dunes Ltd
Defendant
Procedural Posture
Civil Suit / Judgment
Legal Issues
- 1 What were the contractual obligations of the parties under the construction agreement dated 4.11.2008?
- 2 Did the plaintiff fulfil its obligations under the agreement?
- 3 Did the defendant fulfil its obligations under the agreement?
Ratio Decidendi
The court found that both parties breached the original construction agreement: the plaintiff failed to complete the works within the stipulated time, and the defendant failed to make timely payments as requested. The evidence, including expert reports, photographs, and a site visit, established that the main building was substantially complete by October 2011, with only minor defects and some incomplete items (notably the servant quarters, parking, and driveway). The court held that the retention sum (6% of the contract value) was sufficient to cover the cost of rectifying these defects and incomplete works. The plaintiff was not entitled to payment for the servant quarters and parking,...
Court Disposition
Plaintiff's claim partly succeeds; defendant's counter-claim dismissed; each party to bear its own costs.
Orders
- Plaintiff awarded Kshs.8,089,524 as balance due after deductions for uncompleted works and repairs.
- Defendant to take immediate possession of the premises upon payment of the awarded sum.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment