[2015] KEHC 2130 (KLR)

[2015] KEHC 2130 (KLR)

The court found that the plaintiffs failed to meet the threshold for the grant of a mandatory injunction at the interlocutory stage. The construction of the temporary structures was already completed before the application was heard, rendering the prayer for a restraining injunction moot. The issues raised by the...

Source-derived case information.

Citation
[2015] KEHC 2130 (KLR)
Parties
Plaintiff: Rajhnikant Manigal Gohil; Plaintiff: Kamal Manilal Gohil; Plaintiff: Virjajkunver Manilal Govind Gohi; Defendant: County Government of Mombasa
Court
High Court
Court Station
High Court at Mombasa
Jurisdiction
Kenya
Case Number
Environment & Land Case 96 of 2015
Procedural Posture
Environment and Land Case / Ruling on Interlocutory Injunction Application
Outcome
application dismissed
Judges
AA Omollo
Legal Topics
Injunctive Relief, Service Lanes, Temporary Structures, Planning and Development Control
Source Language
en
Land and Property Civil Procedure Injunctive Relief Service Lanes Temporary Structures Planning and Development Control

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 5 Party arguments 2
Sign in to unlock

Parties

Rajhnikant Manigal Gohil

Plaintiff

Kamal Manilal Gohil

Plaintiff

Virjajkunver Manilal Govind Gohi

Plaintiff

County Government of Mombasa

Defendant

Procedural Posture

Environment and Land Case / Ruling on Interlocutory Injunction Application

  1. 1 Whether the plaintiffs are entitled to a temporary injunction restraining the defendant from constructing or erecting structures along the service lane serving their property.
  2. 2 Whether the plaintiffs are entitled to a mandatory injunction directing the defendant to demolish structures already constructed along the service lane.
  3. 3 Whether the defendant's actions amount to unlawful interference with the plaintiffs' property rights.

Ratio Decidendi

The court found that the plaintiffs failed to meet the threshold for the grant of a mandatory injunction at the interlocutory stage. The construction of the temporary structures was already completed before the application was heard, rendering the prayer for a restraining injunction moot. The issues raised by the plaintiffs, including whether the service lane is a road reserve and whether the defendant's actions constituted unlawful interference, require the presentation of evidence at a full trial. The court was unable to determine, based on the affidavits and annexures alone, whether the plaintiffs suffered irreparable harm or whether the defendant's actions were unlawful. Consequently,...

Court Disposition

application dismissed

Orders

  • The application for temporary and mandatory injunctions is dismissed.
  • Each party shall bear their own costs.