The court found that the defendant had obtained a valid wayleave in 1956, which attached to the land and was not challenged for decades. The plaintiffs acquired the suit land in 2010 with full knowledge of the existing power line and subject to pre-existing encumbrances, as evidenced by the certificate of title...

Source-derived case information.

Citation
[2023] KEELC 407 (KLR)
Parties
Plaintiff: Harish Ramji; Plaintiff: Bharat Ramji; Plaintiff: Ashvi Ramji; Defendant: Kenya Power and Lighting Company
Court
Environment and Land Court
Court Station
Environment and Land Court at Machakos
Jurisdiction
Kenya
Case Number
Environment & Land Case 109 of 2015
Procedural Posture
Environment and Land Case / Judgment
Outcome
suit dismissed with costs to the defendant
Judges
CA Ochieng
Legal Topics
Trespass to Land, Wayleave Rights, Land Encumbrances, Burden of Proof
Source Language
en
Land and Property Tort Law Trespass to Land Wayleave Rights Land Encumbrances Burden of Proof

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 12 Party arguments 2
Sign in to unlock

Parties

Harish Ramji

Plaintiff

Bharat Ramji

Plaintiff

Ashvi Ramji

Plaintiff

Kenya Power and Lighting Company

Defendant

Procedural Posture

Environment and Land Case / Judgment

  1. 1 Whether the defendant has trespassed on the plaintiffs’ land.
  2. 2 Whether the plaintiffs are entitled to damages for alleged trespass.
  3. 3 Who should bear the costs of the suit.

Ratio Decidendi

The court found that the defendant had obtained a valid wayleave in 1956, which attached to the land and was not challenged for decades. The plaintiffs acquired the suit land in 2010 with full knowledge of the existing power line and subject to pre-existing encumbrances, as evidenced by the certificate of title referencing the original grant and special conditions. The plaintiffs failed to prove that the defendant constructed new power lines after their acquisition or that the wayleave was invalid. The court held that the wayleave was a valid encumbrance, and there was no actionable trespass. Furthermore, the plaintiffs did not provide evidence of actual loss or approved development plans...

Court Disposition

suit dismissed with costs to the defendant

Orders

  • The plaintiffs' suit is dismissed.