[2001] KEHC 649 (KLR)

[2001] KEHC 649 (KLR)

The court found that the plaintiff had completed the works and was entitled to payment as certified by the defendant's own agents. The defendant failed to provide any evidence of payment or to challenge the validity of the certificate. The court held that the issuance of the final certificate created a binding...

Source-derived case information.

Citation
[2001] KEHC 649 (KLR)
Parties
Plaintiff: Ramji Ratna & Company Ltd.; Defendant: Cotton Board of Kenya
Court
High Court
Court Station
High Court at Nairobi (Milimani Law Courts)
Jurisdiction
Kenya
Case Number
? 1298 of 1990
Procedural Posture
Civil Case / Judgment
Outcome
Judgment for the plaintiff.
Legal Topics
Building Contracts, Final Certificate Payment, Contractual Obligations, Burden of Proof
Source Language
en
Commercial and Corporate Civil Procedure Building Contracts Final Certificate Payment Contractual Obligations Burden of Proof

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Legal principles 2 Authorities cited 1 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Ramji Ratna & Company Ltd.

Plaintiff

Cotton Board of Kenya

Defendant

Procedural Posture

Civil Case / Judgment

  1. 1 Whether the defendant is liable to pay the amount stated in the final Certificate issued by its agent for construction works.
  2. 2 Whether the defendant discharged the burden of proving payment of the outstanding balance to the plaintiff.

Ratio Decidendi

The court found that the plaintiff had completed the works and was entitled to payment as certified by the defendant's own agents. The defendant failed to provide any evidence of payment or to challenge the validity of the certificate. The court held that the issuance of the final certificate created a binding obligation on the defendant to pay the certified sum within the contractual period. The defendant's bare denials and failure to discharge the burden of proof regarding payment meant that the plaintiff's claim was established on a balance of probabilities. Judgment was therefore entered for the plaintiff for the certified sum, with costs and interest.

Court Disposition

Judgment for the plaintiff.

Orders

  • Judgment entered in favour of the plaintiff for Shs.906,414.80 against the defendant.
  • Defendant to pay the plaintiff's costs of the suit.