[2024] KEHC 3264 (KLR)

[2024] KEHC 3264 (KLR)

The court found that while the plaintiff did not complete the works within the original or extended timelines, credible evidence, including a Certificate of Measurement and minutes of joint meetings, established that the works were ultimately completed to the satisfaction of the defendant. The defendant failed to...

Source-derived case information.

Citation
[2024] KEHC 3264 (KLR)
Parties
Plaintiff: Ravina Agencies Limited; Defendant: Coast Water Works Development Agency
Court
High Court
Court Station
High Court at Mombasa
Jurisdiction
Kenya
Case Number
Civil Suit 45A of 2020
Procedural Posture
Civil Suit / Judgment
Outcome
Judgment for the plaintiff.
Judges
OA Sewe
Legal Topics
Breach of Contract, Public Procurement, Liquidated Damages, Contract Variation, Retention Sums
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Public Procurement Liquidated Damages Contract Variation Retention Sums

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 12 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Ravina Agencies Limited

Plaintiff

Coast Water Works Development Agency

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether the plaintiff performed its part of the contract to completion and if the defendant is in breach by failing to pay the balance of the contract sum.
  2. 2 Whether the defendant is in breach by failing to pay the 10% retention sum to the plaintiff.
  3. 3 Whether the defendant illegally deducted Kshs. 4,415,299.88 as liquidated damages from the plaintiff.

Ratio Decidendi

The court found that while the plaintiff did not complete the works within the original or extended timelines, credible evidence, including a Certificate of Measurement and minutes of joint meetings, established that the works were ultimately completed to the satisfaction of the defendant. The defendant failed to provide evidence of any outstanding works or defects. Therefore, the plaintiff was entitled to payment for the balance of the contract sum and the 10% retention sum. However, the deduction of liquidated damages by the defendant was justified under the contract due to the plaintiff's delay, and the plaintiff did not prove entitlement to a refund of those deductions. Interest on...

Court Disposition

Judgment for the plaintiff.

Orders

  • Judgment entered for the plaintiff in the sum of Kshs. 22,446,140.
  • The defendant shall pay interest on the principal sum from the date of judgment until payment in full.