The court found that the plaintiff failed to discharge the burden of proof required to establish that the road was constructed on its private land. The plaintiff did not produce relevant, certified, or official survey maps or plans from government authorities to demonstrate the layout of the property before the road...

Source-derived case information.

Citation
[2023] KEELC 343 (KLR)
Parties
Plaintiff: Registered Trustees of Markaz - Ur – Rashad Trust; Defendant: Kenya Urban Roads Authority (KURA); Defendant: Wak Construction Limited
Court
Environment and Land Court
Court Station
Environment and Land Court at Nairobi
Jurisdiction
Kenya
Case Number
Environment & Land Case 1243 of 2015
Procedural Posture
Environment and Land Case / Judgment
Outcome
suit dismissed
Judges
LN Mbugua
Legal Topics
Compulsory Acquisition, Burden of Proof, Compensation for Land, Evidence Requirements
Source Language
en
Land and Property Civil Procedure Compulsory Acquisition Burden of Proof Compensation for Land Evidence Requirements

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 13 Party arguments 2
Sign in to unlock

Parties

Registered Trustees of Markaz - Ur – Rashad Trust

Plaintiff

Kenya Urban Roads Authority (KURA)

Defendant

Wak Construction Limited

Defendant

Procedural Posture

Environment and Land Case / Judgment

  1. 1 Whether the suit property is private property.
  2. 2 Whether the actions of the 1st defendant to construct a road on the plaintiff’s property amount to constructive compulsory acquisition.
  3. 3 Whether the plaintiff is entitled to compensation for the acquisition of its property.

Ratio Decidendi

The court found that the plaintiff failed to discharge the burden of proof required to establish that the road was constructed on its private land. The plaintiff did not produce relevant, certified, or official survey maps or plans from government authorities to demonstrate the layout of the property before the road construction. The documents provided were undated, unregistered, and prepared by the plaintiff's own architect, lacking evidentiary value. The valuation report relied on the same uncertified documents and did not include an official search or ascertain encumbrances. In the absence of credible, official evidence showing that the road was built on private land, the court held...

Court Disposition

suit dismissed

Orders

  • The suit is dismissed with no orders as to costs.