[2022] KEELC 13714 (KLR)

[2022] KEELC 13714 (KLR)

The court found that the defendant's construction of an additional apartment unit on the rooftop of block B was unlawful and illegal because it was not contemplated in the original plan when the units were sold to the plaintiff and other purchasers. The defendant failed to obtain the consensus of all unit owners, as...

Source-derived case information.

Citation
[2022] KEELC 13714 (KLR)
Parties
Plaintiff: Khalid Hussein Rehman; Defendant: Ahmed Jan Mohamed Suleiman Luhar
Court
Environment and Land Court
Court Station
Environment and Land Court at Mombasa
Jurisdiction
Kenya
Case Number
Environment & Land Case 10 of 2016
Procedural Posture
Environment and Land Case / Judgment
Outcome
Judgment for the plaintiff. Declaration that the construction is unlawful; permanent injunction granted; mandatory injunction for removal of the structure; costs to the plaintiff.
Judges
M Sila
Legal Topics
Sectional Ownership, Common Areas Rights, Development Approvals, Environmental Impact Assessment, Injunctions, Management Company Requirements
Source Language
en
Land and Property Environmental Law Civil Procedure Sectional Ownership Common Areas Rights Development Approvals Environmental Impact Assessment Injunctions +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 10 Party arguments 2
Sign in to unlock

Parties

Khalid Hussein Rehman

Plaintiff

Ahmed Jan Mohamed Suleiman Luhar

Defendant

Procedural Posture

Environment and Land Case / Judgment

  1. 1 Whether the defendant could lawfully construct an additional apartment unit on the rooftop of block B without the consent of other apartment owners.
  2. 2 Whether the defendant obtained all requisite statutory approvals, including an Environmental Impact Assessment (EIA) licence, prior to commencing construction.
  3. 3 Whether the construction violated the rights of the plaintiff and other apartment owners under the Sectional Properties Act and related statutes.

Ratio Decidendi

The court found that the defendant's construction of an additional apartment unit on the rooftop of block B was unlawful and illegal because it was not contemplated in the original plan when the units were sold to the plaintiff and other purchasers. The defendant failed to obtain the consensus of all unit owners, as required under the Sectional Properties Act, and had not established a management company to oversee common areas. Furthermore, the defendant commenced construction without first obtaining an Environmental Impact Assessment (EIA) licence, in violation of section 58 of EMCA. The development approval from the county government was obtained only after construction had started and...

Court Disposition

Judgment for the plaintiff. Declaration that the construction is unlawful; permanent injunction granted; mandatory injunction for removal of the structure; costs to the plaintiff.

Orders

  • A declaration that the ongoing construction by the defendant on the rooftop of block B is unlawful and illegal and must stop immediately.
  • A permanent injunction restraining the defendant from interfering, constructing, alienating, or dealing adversely in any manner whatsoever with the suit property.