[2021] KEHC 1126 (KLR)

[2021] KEHC 1126 (KLR)

The court found that the ex parte Applicant received a clear and express approval from the Ministry of Energy in 2010 to develop a 300MW wind farm, and that this approval was not rescinded. The subsequent imposition of new requirements under the Feed-in-Tariff Policy and Public-Private Partnership Act was unlawful,...

Source-derived case information.

Citation
[2021] KEHC 1126 (KLR)
Parties
Applicant: Gitson Energy Ltd; Respondent: Cabinet Secretary of the National Treasury; Respondent: Ministry of Energy; Respondent: Kenya Power and Lighting Company Ltd; Respondent: Energy Regulatory Commission; Respondent: Kenya Electricity Transmission Company Ltd; Respondent: Attorney General
Court
High Court
Court Station
High Court at Nairobi (Milimani Law Courts)
Jurisdiction
Kenya
Case Number
Judicial Review Miscellaneous Application 324 of 2018
Procedural Posture
Judicial Review Miscellaneous Application / Judgment
Outcome
Application allowed in part. Mandamus issued against the 2nd and 4th Respondents to include the Applicant's project in the approved list and issue permits/licences in line with the 2010 approval. Costs awarded to the Applicant against the 2nd and 4th Respondents. Other prayers declined.
Judges
P Nyamweya
Legal Topics
Judicial Review, Legitimate Expectation, Public Duty, Energy Project Approvals, Licensing and Permits, Public Private Partnerships
Source Language
en
Administrative Law Commercial and Corporate Land and Property Judicial Review Legitimate Expectation Public Duty Energy Project Approvals Licensing and Permits +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 12 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Gitson Energy Ltd

Applicant

Cabinet Secretary of the National Treasury

Respondent

Ministry of Energy

Respondent

Kenya Power and Lighting Company Ltd

Respondent

Energy Regulatory Commission

Respondent

Kenya Electricity Transmission Company Ltd

Respondent

Attorney General

Respondent

Procedural Posture

Judicial Review Miscellaneous Application / Judgment

  1. 1 Whether the Respondents owed the ex parte Applicant a public or statutory duty to process and approve its wind energy project as initially approved in 2010.
  2. 2 Whether the Respondents acted unlawfully or in breach of legitimate expectation by changing the approval terms and imposing new requirements under the Feed-in-Tariff Policy and Public-Private Partnership Act.
  3. 3 Whether the ex parte Applicant was entitled to an order of mandamus compelling the Respondents to include its project in the list of approved projects and issue the necessary permits and licences.

Ratio Decidendi

The court found that the ex parte Applicant received a clear and express approval from the Ministry of Energy in 2010 to develop a 300MW wind farm, and that this approval was not rescinded. The subsequent imposition of new requirements under the Feed-in-Tariff Policy and Public-Private Partnership Act was unlawful, as these frameworks were not applicable at the time of the original approval and could not be applied retrospectively. The Applicant had a legitimate expectation, based on the approval and subsequent conduct of the Respondents, that its project would be processed under the terms initially granted. The Respondents' actions in shifting requirements and failing to process the...

Court Disposition

Application allowed in part. Mandamus issued against the 2nd and 4th Respondents to include the Applicant's project in the approved list and issue permits/licences in line with the 2010 approval. Costs awarded to the Applicant against the 2nd and 4th Respondents. Other prayers declined.

Orders

  • An order of mandamus is issued to compel the 2nd and 4th Respondents to forthwith include the ex parte Applicant’s 300MW Wind Energy Project in the 4th Respondent’s list of approved projects, and to, in consultation with the ex parte Applicant, issue the appropriate permit and licence to the ex parte Applicant in...
  • The 2nd and 4th Respondents shall meet the costs of the ex parte Applicant’s Notice of Motion dated 18th November 2018.