[2019] KEHC 10063 (KLR)

[2019] KEHC 10063 (KLR)

The court found that while the ex parte applicants had performed their contractual obligations and the respondents did not deny the existence of the contracts, the respondents' delay in payment was attributed to ongoing investigations by the EACC into procurement irregularities. The EACC had subsequently issued a...

Source-derived case information.

Citation
[2019] KEHC 10063 (KLR)
Parties
Applicant: Republic; Respondent: Chief Officer of Lands, Infrastructure & Urban Development, County Government of Kitui; Respondent: County Government of Kitui; Applicant: Aridsun Contractors Ltd; Applicant: Katungate Contractors Ltd; Applicant: Syano Roads & Bridges Co. Ltd; Applicant: Kamwando Enterprises Ltd; Applicant: Konza Works Construction & Engineering Ltd; Applicant: Festo Construction & Engineering Company Ltd; Applicant: Watema General Suppliers Ltd; Applicant: Nasicom Logistics Company Ltd; Applicant: Nelly Kavuu Mutisya t/a Kitui General Suppliers & Contractors
Court
High Court
Court Station
High Court at Kitui
Jurisdiction
Kenya
Case Number
Civil Miscellaneous Application 23 of 2018
Procedural Posture
Miscellaneous Application / Judgment
Outcome
Application dismissed. No orders as to costs.
Judges
LN Mutende
Legal Topics
Judicial Review, Mandamus, Fair Administrative Action, Public Procurement, Exhaustion of Remedies
Source Language
en
Administrative Law Civil Procedure Judicial Review Mandamus Fair Administrative Action Public Procurement Exhaustion of Remedies

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 14 Party arguments 2
Sign in to unlock

Parties

Republic

Applicant

Chief Officer of Lands, Infrastructure & Urban Development, County Government of Kitui

Respondent

County Government of Kitui

Respondent

Aridsun Contractors Ltd

Applicant

Katungate Contractors Ltd

Applicant

Syano Roads & Bridges Co. Ltd

Applicant

Kamwando Enterprises Ltd

Applicant

Konza Works Construction & Engineering Ltd

Applicant

Festo Construction & Engineering Company Ltd

Applicant

Watema General Suppliers Ltd

Applicant

Nasicom Logistics Company Ltd

Applicant

Nelly Kavuu Mutisya t/a Kitui General Suppliers & Contractors

Applicant

Procedural Posture

Miscellaneous Application / Judgment

  1. 1 Whether the respondents' delay and failure to process payment for completed contracts violated the ex parte applicants' rights to fair administrative action and property.
  2. 2 Whether an order of mandamus should issue compelling the respondents to process payment for undisputed contractual sums.
  3. 3 Whether the respondents provided sufficient reasons for the delay in payment and if internal remedies were exhausted before seeking judicial review.

Ratio Decidendi

The court found that while the ex parte applicants had performed their contractual obligations and the respondents did not deny the existence of the contracts, the respondents' delay in payment was attributed to ongoing investigations by the EACC into procurement irregularities. The EACC had subsequently issued a letter indicating no objection to payment, provided it was lawful and in accordance with relevant statutes. The court held that the respondents' explanation for delay was plausible and not influenced by extraneous considerations or bad faith. Furthermore, the court emphasized that mandamus is a discretionary remedy and should not be granted where alternative remedies or internal...

Court Disposition

Application dismissed. No orders as to costs.

Orders

  • The orders of mandamus sought are declined.
  • No orders as to costs.