[2021] KEELC 4357 (KLR)

[2021] KEELC 4357 (KLR)

The court found that the Applicants were not challenging the process by which the Respondent arrived at its decision, but rather the merits of the decision itself. The lease agreement granted the Respondent discretion to withhold consent for construction, provided such discretion was not exercised unreasonably. The...

Source-derived case information.

Citation
[2021] KEELC 4357 (KLR)
Parties
Applicant: Republic; Respondent: Kenya Airports Authority; Applicant: Ganshyam Deshabai Patel; Applicant: Sarlaben Gyanshyambhai Patel
Court
Environment and Land Court
Court Station
Environment and Land Court at Nairobi
Jurisdiction
Kenya
Case Number
Environment and Land Judicial Review Case 67 of 2018
Procedural Posture
Judicial Review Application / Judgment
Outcome
application dismissed
Judges
AK Bor
Legal Topics
Public Land Leases, Fair Administrative Action, Judicial Review Remedies, Public Private Partnerships, Legitimate Expectation
Source Language
en
Land and Property Administrative Law Public Land Leases Fair Administrative Action Judicial Review Remedies Public Private Partnerships Legitimate Expectation

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 9 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Republic

Applicant

Kenya Airports Authority

Respondent

Ganshyam Deshabai Patel

Applicant

Sarlaben Gyanshyambhai Patel

Applicant

Procedural Posture

Judicial Review Application / Judgment

  1. 1 Whether the Respondent unreasonably withheld consent for construction under the lease agreement.
  2. 2 Whether the Respondent's decision was based on irrelevant or ulterior considerations contrary to the Fair Administrative Actions Act.
  3. 3 Whether the Applicants are entitled to orders of certiorari and mandamus to quash the Respondent's decision and compel issuance of consent.

Ratio Decidendi

The court found that the Applicants were not challenging the process by which the Respondent arrived at its decision, but rather the merits of the decision itself. The lease agreement granted the Respondent discretion to withhold consent for construction, provided such discretion was not exercised unreasonably. The court determined that the Respondent's decision to withhold consent was based on statutory requirements under the Public Private Partnership Act, public interest considerations, and the need for prudent management of public assets. The Applicants failed to demonstrate that the Respondent acted unreasonably, irrationally, or based its decision on irrelevant or ulterior...

Court Disposition

application dismissed

Orders

  • The application dated 12/7/2018 is dismissed.
  • Each party will bear its own costs.