[2013] KEHC 4965 (KLR)

[2013] KEHC 4965 (KLR)

The court found that the respondent, Municipal Council of Mombasa, had a clear statutory duty under the Physical Planning Act to process and determine the applicant's development approval applications and to communicate its decision within the prescribed period. The respondent's failure to act for over a year,...

Source-derived case information.

Citation
[2013] KEHC 4965 (KLR)
Parties
Applicant: Republic; Respondent: Municipal Council of Mombasa; Respondent: Town Clerk, Municipal Council of Mombasa; Applicant: Kamau J.G. Njengu
Court
High Court
Court Station
High Court at Mombasa
Jurisdiction
Kenya
Case Number
Miscellaneous Civil Application 93 of 2012
Procedural Posture
Miscellaneous Application / Judgment
Outcome
Application allowed. Order of mandamus granted.
Judges
EM Muriithi
Legal Topics
Judicial Review, Mandamus, Development Permissions, Statutory Duties, Fair Administrative Action
Source Language
en
Administrative Law Land and Property Judicial Review Mandamus Development Permissions Statutory Duties Fair Administrative Action

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 3 Party arguments 2
Sign in to unlock

Parties

Republic

Applicant

Municipal Council of Mombasa

Respondent

Town Clerk, Municipal Council of Mombasa

Respondent

Kamau J.G. Njengu

Applicant

Procedural Posture

Miscellaneous Application / Judgment

  1. 1 Whether the respondent had a statutory duty to process and determine the applicant's development approval applications within the prescribed period.
  2. 2 Whether the respondent's failure to act constituted a breach of statutory and constitutional obligations, justifying an order of mandamus.

Ratio Decidendi

The court found that the respondent, Municipal Council of Mombasa, had a clear statutory duty under the Physical Planning Act to process and determine the applicant's development approval applications and to communicate its decision within the prescribed period. The respondent's failure to act for over a year, without providing reasons or a decision, constituted a breach of both statutory obligations and the applicant's constitutional right to fair administrative action under Article 47(1) of the Constitution. The court held that the applicant was entitled to an order of mandamus compelling the respondent to perform its public duty to process and consider the development applications. The...

Court Disposition

Application allowed. Order of mandamus granted.

Orders

  • An order of mandamus is issued compelling the respondent to process and consider the applicant's development approval applications for the specified parcels of land.