[2017] KEHC 9142 (KLR)

[2017] KEHC 9142 (KLR)

The court held that while section 175(1) of the Public Procurement and Asset Disposal Act, 2015 suspends the finality of the Review Board's decision upon commencement of judicial review, it does not create an automatic stay of implementation. Since the decision had already been implemented by the award and execution...

Source-derived case information.

Citation
[2017] KEHC 9142 (KLR)
Parties
Applicant: Transcend Media Group Limited; Respondent: Public Procurement Administrative Review Board; Respondent: Independent Electoral & Boundaries Commission; Respondent: Scanad Kenya Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Law Courts)
Jurisdiction
Kenya
Case Number
Miscellaneous Civil Application 468 of 2017
Procedural Posture
Miscellaneous Application / Ruling on Whether Leave Operates as Stay
Outcome
Leave to commence judicial review granted; application for stay declined.
Judges
GV Odunga
Legal Topics
Judicial Review of Administrative Action, Public Procurement Disputes, Stay of Implementation, Public Interest Override
Source Language
en
Administrative Law Commercial and Corporate Judicial Review of Administrative Action Public Procurement Disputes Stay of Implementation Public Interest Override

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 11 Party arguments 2
Sign in to unlock

Parties

Transcend Media Group Limited

Applicant

Public Procurement Administrative Review Board

Respondent

Independent Electoral & Boundaries Commission

Respondent

Scanad Kenya Limited

Respondent

Procedural Posture

Miscellaneous Application / Ruling on Whether Leave Operates as Stay

  1. 1 Whether the grant of leave to commence judicial review proceedings operates as an automatic stay of the decision of the Public Procurement Administrative Review Board.
  2. 2 Whether public interest considerations override the applicant's request for stay in the context of imminent general elections.
  3. 3 Whether the implementation of the challenged decision renders a stay order nugatory.

Ratio Decidendi

The court held that while section 175(1) of the Public Procurement and Asset Disposal Act, 2015 suspends the finality of the Review Board's decision upon commencement of judicial review, it does not create an automatic stay of implementation. Since the decision had already been implemented by the award and execution of the contract, a stay would be ineffective. Furthermore, the court found that the public interest in ensuring voter education ahead of imminent general elections outweighed the applicant's commercial interests, especially as any loss suffered by the applicant could be compensated by damages. The court emphasized the need to balance private rights with the greater public...

Court Disposition

Leave to commence judicial review granted; application for stay declined.

Orders

  • Leave granted to commence judicial review proceedings shall not operate as a stay of the decision challenged by the ex parte applicant.