[2020] KEHC 9232 (KLR)

[2020] KEHC 9232 (KLR)

The court held that the tender validity period is a mandatory statutory requirement and that once it expires, the procurement process is terminated and cannot be revived by the parties or by an order of the Public Procurement Administrative Review Board. The Respondent acted ultra vires and fell into jurisdictional...

Source-derived case information.

Citation
[2020] KEHC 9232 (KLR)
Parties
Applicant: National Irrigation Board; Respondent: Public Procurement Administrative Review Board; Interested Party: Consortium of GBM Projects Limited and ERG Insaat Ticaret Ve Sanayi A.S.
Court
High Court
Court Station
High Court at Nairobi (Milimani Law Courts)
Jurisdiction
Kenya
Case Number
Judicial Review Miscellaneous Application 103 of 2019
Procedural Posture
Judicial Miscellaneous Application / Judgment
Outcome
application allowed
Judges
JM Mativo
Legal Topics
Public Procurement, Tender Validity, Judicial Review, Administrative Tribunals, Ultra Vires, Bid Evaluation
Source Language
en
Administrative Law Commercial and Corporate Public Procurement Tender Validity Judicial Review Administrative Tribunals Ultra Vires Bid Evaluation

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 11 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

National Irrigation Board

Applicant

Public Procurement Administrative Review Board

Respondent

Consortium of GBM Projects Limited and ERG Insaat Ticaret Ve Sanayi A.S.

Interested Party

Procedural Posture

Judicial Miscellaneous Application / Judgment

  1. 1 Whether the expiry of the tender validity period put to an end the procurement process.
  2. 2 Whether the Public Procurement Administrative Review Board had jurisdiction to extend the validity period of a lapsed tender.
  3. 3 Whether the impugned decision is tainted with bias or illegality.

Ratio Decidendi

The court held that the tender validity period is a mandatory statutory requirement and that once it expires, the procurement process is terminated and cannot be revived by the parties or by an order of the Public Procurement Administrative Review Board. The Respondent acted ultra vires and fell into jurisdictional error by extending the validity period of a lapsed tender, as there was no valid tender to extend. The court further found that the Respondent's decision to substitute the mandatory proof of ownership requirements in the tender documents with alternative documents was inconsistent with the law and the bid documents, rendering the decision illegal. The court rejected the...

Court Disposition

application allowed

Orders

  • An order of certiorari is issued quashing the Respondent's decision dated 21st March 2019 in Request for Review Number 22 of 2019 between Consortium of GBM Projects Limited and ERG Insaat Ticaret Ve Sanayi A.S and National Irrigation Board regarding Tender No. NIB/T/018/2016-2017.
  • No orders as to costs.