[2019] KEELC 4701 (KLR)

[2019] KEELC 4701 (KLR)

The court found that the plaintiff had established a prima facie case by demonstrating acquisition of the suit property in 1989 and providing supporting documentation. The 2nd defendant's evidence of title was not supported by a clear chain of ownership, and its sale agreement referred to unrelated parcels. The...

Source-derived case information.

Citation
[2019] KEELC 4701 (KLR)
Parties
Plaintiff: Resources Enterprises (K) Limited; Defendant: Hon. James Mwangi Gakuya; Defendant: Tresmu Investments Limited
Court
Environment and Land Court
Court Station
Environment and Land Court at Nairobi
Jurisdiction
Kenya
Case Number
? 1262 of 2019
Procedural Posture
Injunction Application / Ruling on Interlocutory Application for Temporary Injunction
Outcome
Plaintiff's application for temporary injunction allowed.
Legal Topics
Ownership Disputes, Injunctive Relief, Title Registration, Trespass, Irreparable Harm
Source Language
en
Land and Property Ownership Disputes Injunctive Relief Title Registration Trespass Irreparable Harm

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 1 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Resources Enterprises (K) Limited

Plaintiff

Hon. James Mwangi Gakuya

Defendant

Tresmu Investments Limited

Defendant

Procedural Posture

Injunction Application / Ruling on Interlocutory Application for Temporary Injunction

  1. 1 Whether the plaintiff has established a prima facie case for grant of a temporary injunction against the defendants.
  2. 2 Whether the plaintiff stands to suffer irreparable harm if the injunction is not granted.
  3. 3 Whether the balance of convenience favours the grant of the injunction.

Ratio Decidendi

The court found that the plaintiff had established a prima facie case by demonstrating acquisition of the suit property in 1989 and providing supporting documentation. The 2nd defendant's evidence of title was not supported by a clear chain of ownership, and its sale agreement referred to unrelated parcels. The court held that the issue of ownership could only be determined at trial, but in the interim, the plaintiff was likely to suffer irreparable harm due to ongoing construction and the risk of the property being disposed of to third parties. The court concluded that it was necessary to preserve the property by restraining further construction pending the hearing and determination of...

Court Disposition

Plaintiff's application for temporary injunction allowed.

Orders

  • Defendants, their agents, employees or servants are restrained from carrying out any further construction on Nairobi/Block 110/339 (Plot No. 748 – THOME 1) pending hearing and determination of the suit or further court orders.
  • Plaintiff to file undertaking as to damages within seven (7) days from the date of the ruling.