[2014] KEELRC 666 (KLR)

[2014] KEELRC 666 (KLR)

The court found that the claimants were engaged as casual labourers on a day-to-day basis for specific construction work, not as continuous employees. The evidence showed they were paid daily, including overtime and double rates for holidays, and were given one day off per week. There was no employment contract or...

Source-derived case information.

Citation
[2014] KEELRC 666 (KLR)
Parties
Applicant: Richard Kiosi and Six Others; Respondent: Alpharama Limited
Court
Employment and Labour Relations Court
Court Station
Employment and Labour Relations Court at Nairobi
Jurisdiction
Kenya
Case Number
Cause 1185 of 2012
Procedural Posture
Employment Cause / Judgment
Outcome
claim dismissed
Legal Topics
Casual Employment, Termination of Employment, Retrenchment, Overtime Pay, Notice Pay, Severance Pay
Source Language
en
Employment and Labour Casual Employment Termination of Employment Retrenchment Overtime Pay Notice Pay Severance Pay

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 2 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

Richard Kiosi and Six Others

Applicant

Alpharama Limited

Respondent

Procedural Posture

Employment Cause / Judgment

  1. 1 Whether the claimants were continuously employed or casual labourers entitled to statutory benefits.
  2. 2 Whether the termination of the claimants' employment was unfair or unlawful.
  3. 3 Whether the claimants are entitled to terminal benefits including notice pay, severance pay, leave, overtime, and house allowance.

Ratio Decidendi

The court found that the claimants were engaged as casual labourers on a day-to-day basis for specific construction work, not as continuous employees. The evidence showed they were paid daily, including overtime and double rates for holidays, and were given one day off per week. There was no employment contract or evidence of continuous service to entitle them to statutory benefits such as notice pay, severance pay, or house allowance. The termination was due to completion of the construction project, a valid reason under the Employment Act. The claimants failed to prove on a balance of probabilities that they were entitled to the reliefs sought. Consequently, their claims were dismissed...

Court Disposition

claim dismissed

Orders

  • The claimants' suit is dismissed in its entirety.