[2020] KEHC 761 (KLR)

[2020] KEHC 761 (KLR)

The court found that while there was a delay in completion of the works, this was attributable to additional and uncontracted works requested by the defendant, not to any breach by the plaintiff. The extension of part 2 of contract 1 was mutually agreed and, if any extra consideration was due, it was subsumed in the...

Source-derived case information.

Citation
[2020] KEHC 761 (KLR)
Parties
Plaintiff: Richfield Engineering Limited; Defendant: Bamburi Cement Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Case 62 of 2010
Procedural Posture
Civil Suit / Judgment
Outcome
Judgment for the plaintiff; counterclaim dismissed.
Judges
F Tuiyott
Legal Topics
Breach of Contract, Special Damages, Variation of Contract, Counterclaim, Interest Awards, Costs of Litigation
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Special Damages Variation of Contract Counterclaim Interest Awards Costs of Litigation

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 3 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Richfield Engineering Limited

Plaintiff

Bamburi Cement Limited

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 What was the scope of each of the three contracts between the parties?
  2. 2 Was contract 3 a variation of contract 1 or an independent contract?
  3. 3 Were there variations to any of the contracts, and if so, were they unilateral or mutual?

Ratio Decidendi

The court found that while there was a delay in completion of the works, this was attributable to additional and uncontracted works requested by the defendant, not to any breach by the plaintiff. The extension of part 2 of contract 1 was mutually agreed and, if any extra consideration was due, it was subsumed in the negotiated price for contract 3. The plaintiff's claim for unrecovered costs due to unlawful extension failed, but the claim for additional works succeeded to the extent of Kshs. 10,007,480.00, as this was a fair pro rata compensation for the extra work admitted by the defendant. The defendant's counterclaim for loss of production and storage charges failed for lack of proof...

Court Disposition

Judgment for the plaintiff; counterclaim dismissed.

Orders

  • Judgment entered for the plaintiff against the defendant for Kshs. 10,007,480.00.
  • Interest on the judgment sum at court rates from the date of filing suit until full payment.