[2023] KEELC 591 (KLR)

[2023] KEELC 591 (KLR)

The court found that the 1st Defendant breached the construction contract by failing to complete the works within the extended timeline, entitling the Plaintiff to terminate the contract lawfully. However, the Plaintiff's claim for Kshs. 140,000,000/- as damages for delay was rejected because the right to such...

Source-derived case information.

Citation
[2023] KEELC 591 (KLR)
Parties
Plaintiff: Ringsview Apartments Limited; Defendant: Vishnu Builders Company Ltd; Defendant: Vijay Morjaria
Court
Environment and Land Court
Court Station
Environment and Land Court at Nairobi
Jurisdiction
Kenya
Case Number
Environment and Land Case Civil Suit 782 of 2014
Procedural Posture
Civil Suit / Judgment
Outcome
Partially allowed for both Plaintiff and Defendants; monetary and injunctive reliefs granted as specified; costs to be borne by each party.
Judges
SO Okong'o
Legal Topics
Construction Contracts, Specific Performance, Fraudulent Conveyancing, Sale of Land, Damages for Delay, Injunctive Relief
Source Language
en
Land and Property Commercial and Corporate Civil Procedure Construction Contracts Specific Performance Fraudulent Conveyancing Sale of Land Damages for Delay +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 11 Party arguments 2 Amounts and remedies 7
Sign in to unlock

Parties

Ringsview Apartments Limited

Plaintiff

Vishnu Builders Company Ltd

Defendant

Vijay Morjaria

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether the 1st Defendant breached the construction contract by failing to complete works within the agreed period.
  2. 2 Whether the Plaintiff is entitled to damages for delay and other monetary claims against the Defendants.
  3. 3 Whether the 2nd Defendant fraudulently obtained registration of certain apartments and unlawfully withheld the title deed.

Ratio Decidendi

The court found that the 1st Defendant breached the construction contract by failing to complete the works within the extended timeline, entitling the Plaintiff to terminate the contract lawfully. However, the Plaintiff's claim for Kshs. 140,000,000/- as damages for delay was rejected because the right to such damages was waived by granting extensions of time. The Plaintiff failed to prove fraud or unlawful withholding of the title deed by the 2nd Defendant, and most monetary claims against the 2nd Defendant were unsubstantiated due to lack of evidence. The court held that the 2nd Defendant and his associates were entitled to apartments for which payment was made, subject to clearing...

Court Disposition

Partially allowed for both Plaintiff and Defendants; monetary and injunctive reliefs granted as specified; costs to be borne by each party.

Orders

  • The 1st Defendant shall return all keys to the residential apartments on L.R No. 4858/11 except as otherwise indicated.
  • The 2nd Defendant is restrained from charging, selling, disposing of, or transferring specified apartments until outstanding balances are cleared.