The court found that the plaintiff had proved, on a balance of probabilities, that it supplied the contracted goods to the Ministry of Health, which were accepted and put into use by the respective hospitals. The defendant, through its witness, admitted the existence of the contract, the supply and acceptance of the...

Source-derived case information.

Citation
[2019] KEHC 12366 (KLR)
Parties
Plaintiff: Rockey Africa Limited; Defendant: The Honourable Attorney General
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Case 198 of 2016
Procedural Posture
Civil Case / Judgment
Outcome
Judgment for the plaintiff.
Judges
WA Okwany
Legal Topics
Breach of Contract, Supply of Goods, Contractual Interest, Government Contracts
Source Language
en
Commercial and Corporate Breach of Contract Supply of Goods Contractual Interest Government Contracts

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 2 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Rockey Africa Limited

Plaintiff

The Honourable Attorney General

Defendant

Procedural Posture

Civil Case / Judgment

  1. 1 Whether the plaintiff proved the supply and delivery of renal dialysis consumables as per the contract.
  2. 2 Whether the defendant breached the contract by failing to pay the contract sum within the stipulated period.
  3. 3 Whether the plaintiff is entitled to the claimed sum and contractual interest for late payment.

Ratio Decidendi

The court found that the plaintiff had proved, on a balance of probabilities, that it supplied the contracted goods to the Ministry of Health, which were accepted and put into use by the respective hospitals. The defendant, through its witness, admitted the existence of the contract, the supply and acceptance of the goods, and the outstanding contract sum. The contract expressly provided for a penalty interest rate of 20% per quarter for late payment. The defendant failed to pay the contract sum within the stipulated period and did not return any alleged excess goods. The court therefore held that the plaintiff was entitled to the contract sum of Kshs 326,891,900 plus accrued interest at...

Court Disposition

Judgment for the plaintiff.

Orders

  • The defendant shall pay the plaintiff Kshs 326,891,900 with accrued interest at the contractual rate of 20% per quarter from 1st July 2012 until payment in full.