[2020] KEELC 2338 (KLR)

[2020] KEELC 2338 (KLR)

The court found that the Plaintiff failed to remit payments as required under the Supplementary Agreement, resulting in her own default and contributing to the delay in completion of the house. The evidence did not support the Plaintiff's claim for penalties, demurrage, or additional damages, as the delay was...

Source-derived case information.

Citation
[2020] KEELC 2338 (KLR)
Parties
Plaintiff: Rossi Renata; Defendant: Fabio Marelli; Defendant: Songhai Investment Ltd; Defendant: Mohamed Essak Bachani
Court
Environment and Land Court
Court Station
Environment and Land Court at Malindi
Jurisdiction
Kenya
Case Number
Environment & Land Case 61 of 2009
Procedural Posture
Civil Suit / Judgment
Outcome
Plaintiff's suit dismissed; judgment for the 3rd Defendant on the counterclaim.
Judges
JO Olola
Legal Topics
Sale of Land, Construction Contracts, Specific Performance, Breach of Contract, Counterclaim, Remedies
Source Language
en
Land and Property Commercial and Corporate Sale of Land Construction Contracts Specific Performance Breach of Contract Counterclaim Remedies

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 3 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Rossi Renata

Plaintiff

Fabio Marelli

Defendant

Songhai Investment Ltd

Defendant

Mohamed Essak Bachani

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether the Defendants breached the agreement to construct and transfer House No. 18 to the Plaintiff within the stipulated period.
  2. 2 Whether the Plaintiff is entitled to penalties, demurrage, special and general damages for alleged delay and breach of contract.
  3. 3 Whether the 3rd Defendant is entitled to the balance of the contract sum as claimed in the Counterclaim.

Ratio Decidendi

The court found that the Plaintiff failed to remit payments as required under the Supplementary Agreement, resulting in her own default and contributing to the delay in completion of the house. The evidence did not support the Plaintiff's claim for penalties, demurrage, or additional damages, as the delay was attributable to her failure to pay, not the Defendants' breach. The 1st and 3rd Defendants were not personally bound by the initial agreement, which was executed by the 2nd Defendant as a separate legal entity. The Plaintiff and her daughter took possession of the house and continue to reside there despite not paying the full contract price. The 3rd Defendant's counterclaim for the...

Court Disposition

Plaintiff's suit dismissed; judgment for the 3rd Defendant on the counterclaim.

Orders

  • Plaintiff's case is dismissed.
  • Judgment entered for the 3rd Defendant in the sum of Kshs 1,950,000/-.