The court found that the Plaintiff failed to demonstrate a prima facie case for most of the orders sought, as the Defendant had obtained the necessary approvals and the alleged illegal excavations had been completed. The Plaintiff did not provide sufficient evidence that the Defendant's construction was within 3-4...

Source-derived case information.

Citation
[2023] KEELC 21565 (KLR)
Parties
Plaintiff: Royal Platinum Management Ltd; Defendant: Royal Modern Homes Ltd
Court
Environment and Land Court
Court Station
Environment and Land Court at Nairobi
Jurisdiction
Kenya
Case Number
Environment & Land Case E065 of 2023
Procedural Posture
Environment and Land Case / Ruling on Interlocutory Applications
Outcome
Plaintiff's application partially allowed; Defendant's application dismissed.
Judges
AA Omollo
Legal Topics
Interlocutory Injunctions, Construction Disputes, Nuisance and Disturbance, Environmental Impact Assessment, Building Approvals, Contempt of Court
Source Language
en
Land and Property Civil Procedure Environmental Law Interlocutory Injunctions Construction Disputes Nuisance and Disturbance Environmental Impact Assessment Building Approvals +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 7 Party arguments 2
Sign in to unlock

Parties

Royal Platinum Management Ltd

Plaintiff

Royal Modern Homes Ltd

Defendant

Procedural Posture

Environment and Land Case / Ruling on Interlocutory Applications

  1. 1 Whether the Plaintiff has met the threshold for grant of interlocutory injunction against the Defendant.
  2. 2 Whether the interim orders of injunction issued should be vacated or maintained.
  3. 3 Whether the Defendant's construction activities were conducted without requisite approvals and in violation of environmental and building regulations.

Ratio Decidendi

The court found that the Plaintiff failed to demonstrate a prima facie case for most of the orders sought, as the Defendant had obtained the necessary approvals and the alleged illegal excavations had been completed. The Plaintiff did not provide sufficient evidence that the Defendant's construction was within 3-4 meters of the boundary wall or that ongoing activities posed imminent danger. However, the court granted an order restraining the Defendant from carrying out construction at night or outside licensed hours, in line with NCA compliance conditions, as a precautionary measure to prevent further disturbance. The remainder of the Plaintiff's prayers and the Defendant's application to...

Court Disposition

Plaintiff's application partially allowed; Defendant's application dismissed.

Orders

  • Defendant restrained from carrying out any construction work (excavation or otherwise) at night or outside licensed hours on L.R No. 209/1451/5.
  • Construction must comply with NCA certificate of compliance conditions.