[2025] KEHC 8708 (KLR)

[2025] KEHC 8708 (KLR)

The court found that despite some agreements lacking the Plaintiff's signature, the conduct of both parties—delivery of goods by the Plaintiff and acceptance and payment by the Defendant—demonstrated a mutual intention to be bound, rendering the contracts valid and enforceable. The Defendant breached the contracts...

Source-derived case information.

Citation
[2025] KEHC 8708 (KLR)
Parties
Plaintiff: Royalken Limited; Defendant: China International Aero-Tech International Engineering Corp
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Suit E455 of 2022
Procedural Posture
Civil Suit / Judgment
Outcome
Judgment for the Plaintiff for special damages and costs; claim for general damages dismissed.
Judges
H Namisi
Legal Topics
Breach of Contract, Special Damages, Interest on Late Payment, Contractual Enforcement
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Special Damages Interest on Late Payment Contractual Enforcement

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 7 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Royalken Limited

Plaintiff

China International Aero-Tech International Engineering Corp

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether there was a valid contract between the parties.
  2. 2 Whether the Defendant breached the contract.
  3. 3 Whether the Plaintiff is entitled to interest as special damages and at what rate.

Ratio Decidendi

The court found that despite some agreements lacking the Plaintiff's signature, the conduct of both parties—delivery of goods by the Plaintiff and acceptance and payment by the Defendant—demonstrated a mutual intention to be bound, rendering the contracts valid and enforceable. The Defendant breached the contracts by failing to pay within the stipulated timelines, and the Plaintiff was entitled to special damages in the form of accrued interest at the contractual rates. However, due to ambiguity in the interest clauses, the court interpreted the penalty as a one-off charge per delayed payment rather than a recurring monthly charge. The court rejected the Plaintiff's claim for general...

Court Disposition

Judgment for the Plaintiff for special damages and costs; claim for general damages dismissed.

Orders

  • Special damages awarded in the sum of Kshs 2,248,508.95 with interest at court rates from the date of filing until payment in full.
  • Costs of the suit awarded to the Plaintiff with interest at court rates from the date of judgment until payment in full.