[2014] KEHC 592 (KLR)

[2014] KEHC 592 (KLR)

The court found that the contract between the parties was partly oral and partly written, with an agreed lump sum for construction works at the factory and residence. There was no binding completion date, and both parties contributed to the breakdown of contractual relations through informal engagement of...

Source-derived case information.

Citation
[2014] KEHC 592 (KLR)
Parties
Plaintiff: Sai Sports Limited; Defendant: Narinder Singh Roopra; Defendant: Surinder Singh Roopra; Defendant: Kulwant Singh Roopra; Defendant: Satnam Singh Roopra
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Case 2022 of 1996
Procedural Posture
Civil Case / Judgment
Outcome
Judgment for the plaintiff in part; counterclaim dismissed.
Legal Topics
Breach of Contract, Construction Contracts, Quantum Meruit, Remedial Damages, Counterclaims, Variation of Contract
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Construction Contracts Quantum Meruit Remedial Damages Counterclaims Variation of Contract

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 3 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

Sai Sports Limited

Plaintiff

Narinder Singh Roopra

Defendant

Surinder Singh Roopra

Defendant

Kulwant Singh Roopra

Defendant

Satnam Singh Roopra

Defendant

Procedural Posture

Civil Case / Judgment

  1. 1 What was the scope and nature of the contract between the parties?
  2. 2 Did either party breach their contractual obligations, and to what extent?
  3. 3 Was there an agreed completion date, and what were the consequences of delay?

Ratio Decidendi

The court found that the contract between the parties was partly oral and partly written, with an agreed lump sum for construction works at the factory and residence. There was no binding completion date, and both parties contributed to the breakdown of contractual relations through informal engagement of professionals and lack of clear documentation. The plaintiff failed to prove that the defendants' delay caused the loss of the Diadora S.p.A. contract or that interest at commercial rates was due. The court accepted the joint expert's valuation of work done and remedial costs, holding that each party should bear half the cost of remedial works. The defendants were underpaid for work done...

Court Disposition

Judgment for the plaintiff in part; counterclaim dismissed.

Orders

  • The plaintiff is awarded Ksh. 1,625,987.50 from the defendants.
  • The principal sum will attract interest at court rates from the date of judgment.