[2018] KECA 882 (KLR)

[2018] KECA 882 (KLR)

The Court of Appeal held that there was no binding agreement on a specific completion date for the construction contract between the parties, as the alleged completion date was referenced only in a letter to the appellant's financier and not mutually agreed at contract formation. The contract was informal, partly...

Source-derived case information.

Citation
[2018] KECA 882 (KLR)
Parties
Appellant: Sai Sports Limited; Respondent: Narinder Singh Roopra; Respondent: Surinder Singh Roopra; Respondent: Kulwant Singh Roopra; Respondent: Satnam Singh Roopra
Court
Court of Appeal
Court Station
Court of Appeal at Nairobi
Jurisdiction
Kenya
Case Number
Civil Appeal 33 of 2017
Procedural Posture
Civil Appeal / Judgment
Outcome
appeal dismissed
Judges
RN Nambuye, DK Musinga
Legal Topics
Building Contracts, Breach of Contract, Remedies for Breach, Quantum of Damages, Expert Evidence, Contractual Timeframes
Source Language
en
Commercial and Corporate Civil Procedure Building Contracts Breach of Contract Remedies for Breach Quantum of Damages Expert Evidence Contractual Timeframes

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 10 Party arguments 2 Amounts and remedies 7
Sign in to unlock

Parties

Sai Sports Limited

Appellant

Narinder Singh Roopra

Respondent

Surinder Singh Roopra

Respondent

Kulwant Singh Roopra

Respondent

Satnam Singh Roopra

Respondent

Procedural Posture

Civil Appeal / Judgment

  1. 1 Whether there was an agreed completion date for the construction contract and if its breach was established.
  2. 2 Whether the respondents failed to perform the works diligently and in accordance with specifications.
  3. 3 Whether the appellant or respondents repudiated the contract and the legal consequences thereof.

Ratio Decidendi

The Court of Appeal held that there was no binding agreement on a specific completion date for the construction contract between the parties, as the alleged completion date was referenced only in a letter to the appellant's financier and not mutually agreed at contract formation. The contract was informal, partly oral and partly written, and lacked essential terms such as completion time. The court found that, in the absence of an express completion date, the law implies a requirement to complete within a reasonable time, which was not shown to have been breached by the respondents. The joint expert's report, which was binding on both parties, established the value of works done and...

Court Disposition

appeal dismissed

Orders

  • The appeal is dismissed with costs to the respondents.