[2020] KEHC 5754 (KLR)

[2020] KEHC 5754 (KLR)

The court found that the plaintiff had established, on a balance of probabilities, that the defendant breached the contract by failing to professionally and satisfactorily complete the contracted works, as evidenced by the inspection report and the uncontested audit report. The loss of profits was specifically...

Source-derived case information.

Citation
[2020] KEHC 5754 (KLR)
Parties
Plaintiff: Samaki Industries (K) Limited; Defendant: Gilfilian Technical Services Limited
Court
High Court
Court Station
High Court at Mombasa
Jurisdiction
Kenya
Case Number
Civil Suit 52 of 1992
Procedural Posture
Civil Suit / Judgment After Formal Proof Following Interlocutory Judgment Due to Default of Appearance and Defence
Outcome
judgment for the plaintiff for proved special damages only; other claims dismissed
Judges
CA Otieno
Legal Topics
Breach of Contract, Damages for Breach, Special Damages, Formal Proof, Default Judgment
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Damages for Breach Special Damages Formal Proof Default Judgment

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Samaki Industries (K) Limited

Plaintiff

Gilfilian Technical Services Limited

Defendant

Procedural Posture

Civil Suit / Judgment After Formal Proof Following Interlocutory Judgment Due to Default of Appearance and Defence

  1. 1 Whether the defendant breached the contract for construction and installation of equipment at the plaintiff's premises.
  2. 2 Whether the plaintiff proved its claim for special damages, including loss of profits, costs of repairs, and further special damages.
  3. 3 Whether general damages are awardable in addition to special damages for breach of contract.

Ratio Decidendi

The court found that the plaintiff had established, on a balance of probabilities, that the defendant breached the contract by failing to professionally and satisfactorily complete the contracted works, as evidenced by the inspection report and the uncontested audit report. The loss of profits was specifically pleaded and supported by an unchallenged audit report, thus meeting the threshold for special damages. However, claims for costs of repairs and further special damages failed for lack of strict proof, as no receipts or supporting documents were produced. The court held that general damages for breach of contract are not awardable where special damages for loss of profits have...

Court Disposition

judgment for the plaintiff for proved special damages only; other claims dismissed

Orders

  • Judgment entered for the plaintiff against the defendant for Kshs 37,343,002 as special damages for loss of profits.
  • Plaintiff's claims for costs of repairs and further special damages are dismissed for lack of proof.