[2013] KEELRC 963 (KLR)

[2013] KEELRC 963 (KLR)

The court found that the claimant was not unfairly terminated but rather failed to resume duty after his arrest. The evidence did not support the claimant's assertion of oral dismissal by the managing director. The respondent's offer of Kshs.95,758.00, comprising salary for August 2012, notice pay, and humanitarian...

Source-derived case information.

Citation
[2013] KEELRC 963 (KLR)
Parties
Applicant: Samuel G. Karitu; Respondent: Crater Automobile (NBI) Limited
Court
Employment and Labour Relations Court
Court Station
Employment and Labour Relations Court at Nakuru
Jurisdiction
Kenya
Case Number
Cause 351 of 2013
Procedural Posture
Employment Cause / Judgment
Outcome
judgment for the claimant in part
Judges
B Ongaya
Legal Topics
Unfair Termination, Summary Dismissal, Terminal Dues, Certificate of Service
Source Language
en
Employment and Labour Unfair Termination Summary Dismissal Terminal Dues Certificate of Service

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 1 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Samuel G. Karitu

Applicant

Crater Automobile (NBI) Limited

Respondent

Procedural Posture

Employment Cause / Judgment

  1. 1 Whether the claimant was unfairly terminated from employment on 13.08.2012.
  2. 2 Whether the claimant is entitled to terminal dues and other reliefs sought.

Ratio Decidendi

The court found that the claimant was not unfairly terminated but rather failed to resume duty after his arrest. The evidence did not support the claimant's assertion of oral dismissal by the managing director. The respondent's offer of Kshs.95,758.00, comprising salary for August 2012, notice pay, and humanitarian service pay (less deductions and salary advance), was deemed reasonable and just. The claimant was therefore entitled to this sum, 50% of the costs, and a certificate of service, but all other claims failed.

Court Disposition

judgment for the claimant in part

Orders

  • The respondent to pay the claimant Kshs.95,758.00 by 24.12.2013, failing which interest is payable at court rates from the date of judgment.