[2020] KEHC 5469 (KLR)

[2020] KEHC 5469 (KLR)

The court found that a binding contract existed between the plaintiff and defendants for the construction of the multi-storey classroom block (Bill 1), with the possibility of subsequent phases subject to further agreement and funding. The defendants' termination of the contract before expiry was unlawful and...

Source-derived case information.

Citation
[2020] KEHC 5469 (KLR)
Parties
Plaintiff: Security Products Limited; Defendant: Gabriel Teo Kian Chong; Defendant: Tana River Life Foundation
Court
High Court
Court Station
High Court at Malindi
Jurisdiction
Kenya
Case Number
Civil Suit 7 of 2014
Procedural Posture
Civil Suit / Judgment
Outcome
Plaintiff's claim partially succeeds; damages awarded for proven heads only.
Judges
DB Nyakundi
Legal Topics
Breach of Contract, Building and Construction Contracts, Damages Assessment, Contractual Liability, Tender Process, Termination of Contract
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Building and Construction Contracts Damages Assessment Contractual Liability Tender Process Termination of Contract

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 25 Party arguments 2 Amounts and remedies 4
Sign in to unlock

Parties

Security Products Limited

Plaintiff

Gabriel Teo Kian Chong

Defendant

Tana River Life Foundation

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether there was a binding building contract between the plaintiff and defendants for the entire project or only for phase one.
  2. 2 Whether the defendants unlawfully repudiated the contract before expiry of the contract period.
  3. 3 Whether the plaintiff is entitled to damages for breach of contract and, if so, the quantum and heads of such damages.

Ratio Decidendi

The court found that a binding contract existed between the plaintiff and defendants for the construction of the multi-storey classroom block (Bill 1), with the possibility of subsequent phases subject to further agreement and funding. The defendants' termination of the contract before expiry was unlawful and amounted to repudiation. The plaintiff was entitled to damages for breach of contract, but only for the value of works performed, unpaid invoices, and proven loss of income and profits related to Bill 1. Claims for demobilization and worker payments were dismissed for lack of proof. The court emphasized that special damages must be specifically pleaded and strictly proved, and that...

Court Disposition

Plaintiff's claim partially succeeds; damages awarded for proven heads only.

Orders

  • Plaintiff awarded Kshs.6,202,232.55 for loss of income and profits.
  • Plaintiff awarded Kshs.4,757,309.02 for unpaid invoices.