The court found that although the applicant was the registered proprietor of the suit property and had obtained some approvals, he failed to secure the mandatory change of user approval and commenced construction before obtaining the National Construction Authority's approval. The approval from the County Government...

Source-derived case information.

Citation
[2017] KEELC 3685 (KLR)
Parties
Applicant: Shahzid Ahmed Yusuf; Respondent: The County Government of Kilifi
Court
Environment and Land Court
Court Station
Environment and Land Court at Malindi
Jurisdiction
Kenya
Case Number
Environment & Land Case 95 of 2016
Procedural Posture
Civil Application / Ruling on Interlocutory Injunction Application
Outcome
application dismissed
Judges
OA Angote
Legal Topics
Temporary Injunctions, Land Use Approvals, Change of User, Building Permissions
Source Language
en
Land and Property Civil Procedure Temporary Injunctions Land Use Approvals Change of User Building Permissions

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 3 Party arguments 2
Sign in to unlock

Parties

Shahzid Ahmed Yusuf

Applicant

The County Government of Kilifi

Respondent

Procedural Posture

Civil Application / Ruling on Interlocutory Injunction Application

  1. 1 Whether the applicant is entitled to a temporary injunction restraining the respondent from interfering with construction on the suit property.
  2. 2 Whether the applicant obtained all necessary approvals, including change of user and National Construction Authority approval, prior to commencing construction.
  3. 3 Whether the applicant has established a prima facie case with a probability of success.

Ratio Decidendi

The court found that although the applicant was the registered proprietor of the suit property and had obtained some approvals, he failed to secure the mandatory change of user approval and commenced construction before obtaining the National Construction Authority's approval. The approval from the County Government was conditional upon securing change of user and other departmental approvals, which were not fulfilled. The belated approval from the National Construction Authority was obtained after the respondent's stop notice. In the absence of these essential approvals, the applicant failed to establish a prima facie case with a probability of success, and thus did not meet the...

Court Disposition

application dismissed

Orders

  • The application dated 26th April, 2016 is dismissed with costs to the respondent.