[2020] KEHC 9607 (KLR)

[2020] KEHC 9607 (KLR)

The court found that, while the Energy Act, 2019 vests jurisdiction for disputes between licensees and third parties in the Energy and Petroleum Tribunal, the Tribunal had not yet been constituted at the time of the application. The court agreed with the plaintiff that it would be remiss to deny interim protection...

Source-derived case information.

Citation
[2020] KEHC 9607 (KLR)
Parties
Plaintiff: Shalimar Limited; Defendant: Kenya Power & Lighting Company Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Suit E123 of 2019
Procedural Posture
Civil Suit / Ruling on Preliminary Objection and Interim Injunction Extension
Outcome
Interim injunction extended; matter to be mentioned for status of Tribunal; liberty to apply for transfer; no costs on preliminary objection.
Judges
MM Kasango
Legal Topics
Jurisdiction of Tribunals, Energy Sector Disputes, Interim Injunctions
Source Language
en
Commercial and Corporate Civil Procedure Jurisdiction of Tribunals Energy Sector Disputes Interim Injunctions

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 6 Party arguments 2
Sign in to unlock

Parties

Shalimar Limited

Plaintiff

Kenya Power & Lighting Company Limited

Defendant

Procedural Posture

Civil Suit / Ruling on Preliminary Objection and Interim Injunction Extension

  1. 1 Whether the High Court has jurisdiction to hear disputes between a licensee and a third party under the Energy Act, 2019.
  2. 2 Whether the matter should be referred to the Energy and Petroleum Tribunal as provided by statute.
  3. 3 Whether interim injunctive relief should be maintained pending constitution of the Tribunal.

Ratio Decidendi

The court found that, while the Energy Act, 2019 vests jurisdiction for disputes between licensees and third parties in the Energy and Petroleum Tribunal, the Tribunal had not yet been constituted at the time of the application. The court agreed with the plaintiff that it would be remiss to deny interim protection in the absence of an operational Tribunal. Therefore, the interim injunction restraining the defendant from disconnecting electricity supply was extended until the Tribunal is constituted, after which the matter may be transferred to the appropriate forum. The court emphasized the need to follow statutory procedures but recognized the necessity of temporary judicial intervention...

Court Disposition

Interim injunction extended; matter to be mentioned for status of Tribunal; liberty to apply for transfer; no costs on preliminary objection.

Orders

  • The interim injunction granted to the plaintiff on 16th May 2019 is extended up to 28th May 2020.
  • This matter shall be mentioned on 28th May 2020 for the parties to inform the court whether the Energy and Petroleum Tribunal has been constituted.