[2023] KEELC 16932 (KLR)

[2023] KEELC 16932 (KLR)

The court held that the primary complaints in the suit related to the legality and compliance of the defendant's construction with statutory approvals and procedures, matters which fall under the jurisdiction of statutory bodies established by the Physical and Land Use Planning Act and the Environment Management and...

Source-derived case information.

Citation
[2023] KEELC 16932 (KLR)
Parties
Plaintiff: Devendra Jakumar Sheth; Defendant: Ahmaduna Housing Properties Limited
Court
Environment and Land Court
Court Station
Environment and Land Court at Mombasa
Jurisdiction
Kenya
Case Number
Environment & Land Case E010 of 2023
Procedural Posture
Environment and Land Case / Ruling on Preliminary Objection and Interlocutory Applications
Outcome
Preliminary objection upheld; suit and applications struck out for want of jurisdiction; costs awarded to defendant.
Judges
SM Kibunja
Legal Topics
Injunctive Relief, Nuisance, Jurisdiction of Elc, Statutory Dispute Resolution, Building Approvals, Environmental Impact Assessment
Source Language
en
Land and Property Civil Procedure Injunctive Relief Nuisance Jurisdiction of Elc Statutory Dispute Resolution Building Approvals Environmental Impact Assessment

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 14 Party arguments 2
Sign in to unlock

Parties

Devendra Jakumar Sheth

Plaintiff

Ahmaduna Housing Properties Limited

Defendant

Procedural Posture

Environment and Land Case / Ruling on Preliminary Objection and Interlocutory Applications

  1. 1 Whether the Environment and Land Court has jurisdiction to hear and determine the issues raised in the suit in light of statutory dispute resolution mechanisms.
  2. 2 Whether the plaintiff has met the threshold for the grant of injunction orders sought.
  3. 3 Who should bear the costs of the applications.

Ratio Decidendi

The court held that the primary complaints in the suit related to the legality and compliance of the defendant's construction with statutory approvals and procedures, matters which fall under the jurisdiction of statutory bodies established by the Physical and Land Use Planning Act and the Environment Management and Co-ordination Act. The court found that the plaintiff had not exhausted the dispute resolution mechanisms provided by these statutes, such as the County Physical and Land Use Liaison Committee and the National Environment Tribunal. In line with the doctrine of judicial restraint and the principle that jurisdiction must be established before any substantive determination, the...

Court Disposition

Preliminary objection upheld; suit and applications struck out for want of jurisdiction; costs awarded to defendant.

Orders

  • The defendant's preliminary objection dated March 16, 2023 is upheld.
  • The plaintiff's applications dated February 13 and 17, 2023 and the suit commenced through the plaint dated February 13, 2023 are struck out with costs to the defendant.