[2007] KEHC 3714 (KLR)
The court found that the plaintiff's claim, arising from a building construction agreement terminated on 23/3/93, was subject to a six-year limitation period under Section 4(1) of the Limitation of Actions Act. The suit, filed on 21/7/04, was well outside this period. Even considering alleged new causes of action...
Source-derived case information.
- Citation
- [2007] KEHC 3714 (KLR)
- Parties
- Plaintiff: Shivji Ruda t/a Ajit Construction Company Limited; Respondent: National Housing Corporation
- Court
- High Court
- Court Station
- High Court at Nairobi (Milimani Law Courts)
- Jurisdiction
- Kenya
- Case Number
- Civil Case 407 of 2004
- Procedural Posture
- Civil Case / Ruling on Chamber Summons to Strike Out Plaint for Being Time Barred
- Outcome
- Plaint struck out and suit dismissed as time-barred; costs awarded to defendant; leave to appeal denied.
- Legal Topics
- Limitation of Actions, Contractual Disputes, Striking Out Pleadings
- Source Language
- en
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Shivji Ruda t/a Ajit Construction Company Limited
Plaintiff
National Housing Corporation
Respondent
Procedural Posture
Civil Case / Ruling on Chamber Summons to Strike Out Plaint for Being Time Barred
Legal Issues
- 1 Whether the plaintiff's suit is time-barred under Section 4(1) of the Limitation of Actions Act.
- 2 Whether any new cause of action arose that would extend the limitation period.
- 3 Whether the invocation of arbitration can revive a time-barred claim.
Ratio Decidendi
The court found that the plaintiff's claim, arising from a building construction agreement terminated on 23/3/93, was subject to a six-year limitation period under Section 4(1) of the Limitation of Actions Act. The suit, filed on 21/7/04, was well outside this period. Even considering alleged new causes of action from later meetings or payments, the latest possible limitation expired on 12/11/03. The court held that both the original and any alleged new causes of action were time-barred. The court further held that the arbitration clause could not be invoked to revive a time-barred claim. The plaintiff's reliance on D'Silva v. Rahimtulla was misplaced, as that case concerned restitution...
Court Disposition
Plaint struck out and suit dismissed as time-barred; costs awarded to defendant; leave to appeal denied.
Orders
- The plaint dated 21/7/04 is struck out and the suit dismissed for being time-barred.
- Costs of the application and the suit to be paid by the plaintiff/respondent.
Full Case Text
Judgment text and source record
31 paragraphs
REPUBLIC OF KENYA
IN THE HIGH COURT OF KENYA AT NAIROBI
MILIMANI LAW COURTS
Civil Case 407 of 2004
SHIVJI RUDA t/a AJIT CONSTRUCTION COMPANY LIMITED…,,,,…PLAINTIFF
VERSUS
NATIONAL HOUSING CORPORATION ………..........................…. RESPONDENT
R U L I N G
This Chamber Summons, dated and filed, on 29/10/04, is under order 6 Rule 13(1) (b) (c ) and (d) of the Civil Procedure Rules, and seeks the following orders:
1. That the plaint herein, dated and filed on 21/7/04, by the Plaintiff, be struck out and the suit dismissed with costs to the Defendant.
2. Costs of this application to be paid by the Plaintiff.
Supported by an Affidavit by W.K.B. Keitany, the application is on the grounds, inter alia, that: the cause of action arose from a Building Construction Agreement entered between the parties on 18/5/1990; final accounts were signed and the project handed over (uncompleted) on 23/3/93 and the plaintiff’s claim arises from the non-settlement of those accounts, which forms the date the cause of action accrued; any action could only be brought within 6 years on or before 22/3/1999, as per Section 4(1) of the Limitation of Actions Act, Cap. 22, Laws of Kenya
if a new cause of action arose from the meeting of the parties on 30/5/96, final certificate No. 13 dated 4/9/97, or payment of K.Shs.1,000,000/- on 13/11/97, any suit arising therefrom could only be brought on or before 12/11/03. This suit was brought on 21/7/04, totally out of time, and without leave or extension of time, and it is frivolous, vexatious, scandalous and only meant to prejudice and embarrass the Defendant; it is an abuse of the due process of the court.
In opposition, the Respondent/Plaintiff filed grounds of objection on 26/11/04, which I have carefully considered.
Taking the pleadings herein and the submissions by learned counsel for both sides, I have reached the following findings and conclusions.
This is a case based on contract between the parties as per the agreement dated 18/5/90. Under Section 4(1) of the Limitation of Actions Act, any breach from such a contract must be prosecuted within 6 years of the cause of action, on pain of the suit being time barred.
The evidence before me shows that the Agreement was terminated on23/3/93. The suit should have been instituted on 23/3/1999. Here the suit was filed on 21/7/04 – way beyond the statutory limitation period of 6 years.
Even the alleged new cause of action on 30/5/96,that would also be time barred after 30/5/02. All in all, I hold that both the original cause of action, and the alleged new cause of action, are time barred, and are not tenable in law.
I need also add that the invocation of arbitration is of no assistance to the Plaintiff. Arbitration is generally a clause in a contract, and if not invoked within the statutory period of 6 years, the matter cannot be referred to arbitration when the suit is time barred.
The Plaintiff/Respondent sought to rely on the case of D’SILVA V. RAHIMTULLA, [1968] E.A. 287. My reading of that case is that it deals with restitution – a claim for money from a void land transaction, which meant that from the word go, there was no legal basis of the money that had changed hands. The transaction was void ab-initio and the money could not be held without consideration or valid transaction. In contracts, the time begins to run from breach.
All in all therefore, I rule as under:
1. Grant the prayers in the Chamber Summons herein, dated 29/10/2004, and strike out the suit and dismiss the same, for being time barred.
2. Order that the costs of both this application and the suit herein be paid by the Plaintiff/Respondent.
DATED and delivered in Nairobi, this 28th day of March, 2007.
O.K. MUTUNGI
JUDGE
Mr. Mwangi: We apply for leave to appeal against the ruling just delivered.
Ruling:
Leave to appeal NOT granted, as such an action would further delay a matter already delayed. Litigation must come to an end.
O.K. MUTUNGI
JUDGE