[2025] KEELC 3866 (KLR)

[2025] KEELC 3866 (KLR)

The court found that the interim order of status quo was properly issued to preserve the suit land pending the hearing of the substantive contempt application, given the prima facie evidence of ongoing construction works by the Respondents. The court held that the 1st Respondent had not demonstrated sufficient cause...

Source-derived case information.

Citation
[2025] KEELC 3866 (KLR)
Parties
Applicant: Simonash Investment Ltd; Respondent: Kenya National Highway Authority; Respondent: National Land Commission; Respondent: Honourable Attorney General
Court
Environment and Land Court
Court Station
Environment and Land Court at Kisumu
Jurisdiction
Kenya
Case Number
Constitutional Petition 15 of 2019
Procedural Posture
Constitutional Petition / Ruling on Interlocutory Application for Stay of Execution/enforcement of Interim Orders
Outcome
application dismissed
Judges
E Asati
Legal Topics
Contempt of Court, Interim Injunctions, Right to Property, Enforcement of Judgments
Source Language
en
Land and Property Constitutional Law Contempt of Court Interim Injunctions Right to Property Enforcement of Judgments

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 5 Party arguments 2
Sign in to unlock

Parties

Simonash Investment Ltd

Applicant

Kenya National Highway Authority

Respondent

National Land Commission

Respondent

Honourable Attorney General

Respondent

Procedural Posture

Constitutional Petition / Ruling on Interlocutory Application for Stay of Execution/enforcement of Interim Orders

  1. 1 Whether the 1st Respondent is entitled to a stay of execution or enforcement of the interim order of status quo granted on 28/4/2025.
  2. 2 Whether the short notice given to the 1st Respondent for the mention on 28/4/2025 justified setting aside or staying the interim orders.
  3. 3 Whether the interim order of status quo was properly issued pending hearing of the substantive contempt application.

Ratio Decidendi

The court found that the interim order of status quo was properly issued to preserve the suit land pending the hearing of the substantive contempt application, given the prima facie evidence of ongoing construction works by the Respondents. The court held that the 1st Respondent had not demonstrated sufficient cause to warrant a stay of execution or enforcement of the interim order, as the order was limited to stopping further excavation, construction, or developments on the suit land and did not affect the construction of the Kisumu-Kakamega-Webuye-Kitale Highway. The court further noted that the substantive application had not yet been heard and that the directions given on 28/4/2025...

Court Disposition

application dismissed

Orders

  • The 1st Respondent's application dated 2nd May 2025 is dismissed.
  • No order as to costs.