[2022] KEHC 10682 (KLR)

[2022] KEHC 10682 (KLR)

The High Court found that the respondents failed to discharge the burden of proof required to establish breach of contract and entitlement to special damages. The evidence presented by the respondents was inconsistent and lacked credible support regarding the procurement and existence of the 440 lorry-loads of...

Source-derived case information.

Citation
[2022] KEHC 10682 (KLR)
Parties
Appellant: Sinohydro Tianjin Engineering Company Limited; Respondent: Robert Njuki Kiarie; Respondent: Peter Waithaka Kamau; Respondent: Danson Karanja Kamau; Respondent: Peter Kimemia Njeri t/a Ropedda Transport Services
Court
High Court
Court Station
High Court at Nairobi (Milimani Law Courts)
Jurisdiction
Kenya
Case Number
Civil Appeal 8 of 2020
Procedural Posture
Civil Appeal / Judgment
Outcome
appeal_allowed
Judges
CW Meoli
Legal Topics
Breach of Contract, Burden of Proof, Special Damages, Contract Termination
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Burden of Proof Special Damages Contract Termination

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 21 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Sinohydro Tianjin Engineering Company Limited

Appellant

Robert Njuki Kiarie

Respondent

Peter Waithaka Kamau

Respondent

Danson Karanja Kamau

Respondent

Peter Kimemia Njeri t/a Ropedda Transport Services

Respondent

Procedural Posture

Civil Appeal / Judgment

  1. 1 Whether the appellant breached the contract for supply of murram material with the respondents.
  2. 2 Whether the respondents proved their claim for special damages arising from the alleged breach of contract.
  3. 3 Whether the trial court erred in shifting the burden of proof to the appellant.

Ratio Decidendi

The High Court found that the respondents failed to discharge the burden of proof required to establish breach of contract and entitlement to special damages. The evidence presented by the respondents was inconsistent and lacked credible support regarding the procurement and existence of the 440 lorry-loads of murram, the date and manner of contract termination, and the loss allegedly suffered. The trial court erred by shifting the burden of proof to the appellant and by treating the claim as automatically established upon proof of breach, without requiring strict proof of special damages. The appellate court held that the respondents neither proved breach nor loss as required by law, and...

Court Disposition

appeal_allowed

Orders

  • The appeal is allowed.
  • The judgment of the lower court is set aside in its entirety.