[2020] KEHC 9470 (KLR)

[2020] KEHC 9470 (KLR)

The court found that the plaintiff had proved, on a balance of probabilities, the existence of a contract with the defendant for the execution of office fit out works, that the works were completed, and that a balance remained unpaid. The defendant's denials and allegations were not supported by any evidence, as the...

Source-derived case information.

Citation
[2020] KEHC 9470 (KLR)
Parties
Plaintiff: Specialized Aluminium Renovators Limited; Defendant: Inform Creative Interiors Limited
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Suit 416 of 2009
Procedural Posture
Civil Suit / Judgment
Outcome
Judgment for the plaintiff.
Judges
GMA Dulu
Legal Topics
Breach of Contract, Construction Contracts, Specific Damages, Vat Liability
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Construction Contracts Specific Damages Vat Liability

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 3 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Specialized Aluminium Renovators Limited

Plaintiff

Inform Creative Interiors Limited

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether there was a valid contract between the plaintiff and the defendant for the office fit out works at ZEP RE Centre.
  2. 2 Whether the defendant breached the contract by failing to pay the outstanding sum to the plaintiff.
  3. 3 Whether the plaintiff is entitled to the claimed sum, VAT, costs, and interest.

Ratio Decidendi

The court found that the plaintiff had proved, on a balance of probabilities, the existence of a contract with the defendant for the execution of office fit out works, that the works were completed, and that a balance remained unpaid. The defendant's denials and allegations were not supported by any evidence, as the defendant did not attend the hearing or call witnesses. The court held that the plaintiff was entitled to the outstanding contractual sum, including VAT, as the contract was exclusive of VAT and the plaintiff would be liable for the tax. The court further held that costs and interest should be awarded to the plaintiff as the successful party. The claim for general damages was...

Court Disposition

Judgment for the plaintiff.

Orders

  • Judgment entered in favour of the plaintiff against the defendant in the sum of Kshs.3,250,646.04 inclusive of 16% VAT.
  • The defendant shall pay costs of the suit to the plaintiff.