[2017] KEHC 6732 (KLR)

[2017] KEHC 6732 (KLR)

The court found that the defendant was in breach of contract by failing to hand over the site to the plaintiff, as evidenced by correspondence and the defendant's conduct. The plaintiff was entitled to damages for breach of contract, including costs incurred in preparing for performance (performance bond, loan...

Source-derived case information.

Citation
[2017] KEHC 6732 (KLR)
Parties
Plaintiff: Speed Wall Building Technologies Ltd; Defendant: The County Government of Migori
Court
High Court
Court Station
High Court at Migori
Jurisdiction
Kenya
Case Number
Civil Case 01 of 2016
Procedural Posture
Civil Case / Judgment
Outcome
judgment for the plaintiff
Legal Topics
Breach of Contract, Damages Assessment, Performance Bond, Liquidated Damages
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Damages Assessment Performance Bond Liquidated Damages

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 9 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Speed Wall Building Technologies Ltd

Plaintiff

The County Government of Migori

Defendant

Procedural Posture

Civil Case / Judgment

  1. 1 Whether the defendant breached the contract by failing to hand over the site to the plaintiff.
  2. 2 Whether the plaintiff is entitled to general and special damages for breach of contract.
  3. 3 Whether the plaintiff is entitled to liquidated damages and other claimed sums.

Ratio Decidendi

The court found that the defendant was in breach of contract by failing to hand over the site to the plaintiff, as evidenced by correspondence and the defendant's conduct. The plaintiff was entitled to damages for breach of contract, including costs incurred in preparing for performance (performance bond, loan charges, and bank fees) up to the point where it should have mitigated its losses. Claims for anticipated profits, professional fees, and other special damages were denied as they were not specifically pleaded or proved, and no actual expenditure was incurred. The court awarded general damages for breach of contract, interest at court rates from the date of filing suit, and costs to...

Court Disposition

judgment for the plaintiff

Orders

  • The defendant shall pay the plaintiff Kshs. 2,280,003 as general damages for breach of contract.
  • Interest on the awarded sum at court rates from the date of filing suit until payment in full.