[2019] KEELC 4046 (KLR)

[2019] KEELC 4046 (KLR)

The court found that the petition, though framed as a constitutional claim, was in substance a challenge to a decision made by the 2nd respondent company regarding property management, specifically the replacement of the makuti roof and associated costs. As the petitioner was a shareholder and member of the company,...

Source-derived case information.

Citation
[2019] KEELC 4046 (KLR)
Parties
Applicant: Spencer Gelsthorpe; Respondent: Valentina Berttoncelli; Respondent: Lawfords Management Limited; Respondent: Global Services and Management Limited
Court
Environment and Land Court
Court Station
Environment and Land Court at Malindi
Jurisdiction
Kenya
Case Number
Petition 7 of 2018
Procedural Posture
Constitutional Petition / Ruling on Preliminary Objection
Outcome
Petition struck out on preliminary objection; costs awarded to respondents.
Judges
JO Olola
Legal Topics
Shareholder Rights, Company Management, Property Rights, Derivative Actions
Source Language
en
Land and Property Commercial and Corporate Shareholder Rights Company Management Property Rights Derivative Actions

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 6 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Spencer Gelsthorpe

Applicant

Valentina Berttoncelli

Respondent

Lawfords Management Limited

Respondent

Global Services and Management Limited

Respondent

Procedural Posture

Constitutional Petition / Ruling on Preliminary Objection

  1. 1 Whether the petitioner has locus standi to bring a constitutional petition in respect of company decisions made by the 2nd respondent.
  2. 2 Whether the petition is in substance a derivative suit requiring compliance with the Companies Act, 2015.
  3. 3 Whether the actions of the respondents violated the petitioner's constitutional rights under Articles 29 and 40.

Ratio Decidendi

The court found that the petition, though framed as a constitutional claim, was in substance a challenge to a decision made by the 2nd respondent company regarding property management, specifically the replacement of the makuti roof and associated costs. As the petitioner was a shareholder and member of the company, his remedy for disagreement with company decisions lay in internal company processes, such as persuading other shareholders to overturn the resolution, or by following the statutory procedure for derivative actions under the Companies Act, 2015. The petitioner failed to demonstrate any illegality or inability of the company to act, nor did he comply with the mandatory...

Court Disposition

Petition struck out on preliminary objection; costs awarded to respondents.

Orders

  • The petition dated 18th April 2018 is struck out.
  • The respondents shall have the costs of the petition.