[2024] KEHC 5928 (KLR)

[2024] KEHC 5928 (KLR)

The court found that although there was a delay in dispatching ballot papers, the plaintiff failed to prove any lawful variation of the contract entitling it to additional compensation. The purported agreement to pay for four extra days was not supported by written approval from the defendant's Tender Committee as...

Source-derived case information.

Citation
[2024] KEHC 5928 (KLR)
Parties
Plaintiff: Spero Africa Limited; Defendant: Independent Electoral and Boundaries Commission
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Suit 56 of 2016
Procedural Posture
Civil Suit / Judgment
Outcome
suit dismissed with costs to the defendant
Judges
FG Mugambi
Legal Topics
Public Procurement Contracts, Contract Variation, Tender Disputes, Statutory Compliance, Illegality of Contracts, Remedies for Breach
Source Language
en
Commercial and Corporate Civil Procedure Administrative Law Public Procurement Contracts Contract Variation Tender Disputes Statutory Compliance Illegality of Contracts +1 more

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 5 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Spero Africa Limited

Plaintiff

Independent Electoral and Boundaries Commission

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether there was a material alteration of the contract terms between the parties for the transportation of ballot papers.
  2. 2 Whether the plaintiff is entitled to compensation for the delay in dispatching the ballot papers beyond the original contract period.

Ratio Decidendi

The court found that although there was a delay in dispatching ballot papers, the plaintiff failed to prove any lawful variation of the contract entitling it to additional compensation. The purported agreement to pay for four extra days was not supported by written approval from the defendant's Tender Committee as required by the Public Procurement and Disposal Act and Regulations. The court held that any variation of a public procurement contract must strictly comply with statutory requirements, including approval and adherence to quantity and timing limits. Since the contract had already been performed and paid in full, and no statutory compliance for variation was demonstrated, the...

Court Disposition

suit dismissed with costs to the defendant

Orders

  • The suit is dismissed with costs to the defendant.