[2019] KEHC 1529 (KLR)

[2019] KEHC 1529 (KLR)

The court found that the relationship between the parties had irretrievably broken down, as evidenced by the defendant's notice of termination. The court held that damages would be an adequate remedy for the plaintiff in the event of wrongful termination, and it would not be appropriate to force the defendant to...

Source-derived case information.

Citation
[2019] KEHC 1529 (KLR)
Parties
Plaintiff: Stansha Limited; Defendant: Athi Water Works Development Agency
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Case E420 of 2019
Procedural Posture
Civil Case / Ruling on Interim Measures of Protection Pending Arbitration
Outcome
Application for interim injunctions largely declined; limited order granted for valuation of works.
Judges
DAS Majanja
Legal Topics
Interim Injunctions, Arbitration Referral, Construction Contracts, Performance Bonds
Source Language
english
Commercial and Corporate Civil Procedure Interim Injunctions Arbitration Referral Construction Contracts Performance Bonds

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 1 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Stansha Limited

Plaintiff

Athi Water Works Development Agency

Defendant

Procedural Posture

Civil Case / Ruling on Interim Measures of Protection Pending Arbitration

  1. 1 Whether the plaintiff is entitled to interim measures of protection pending arbitration under section 7 of the Arbitration Act.
  2. 2 Whether damages are an adequate remedy for the plaintiff in the event of contract termination.
  3. 3 Whether the defendant should be restrained from recalling the performance bond and advance payment guarantee pending arbitration.

Ratio Decidendi

The court found that the relationship between the parties had irretrievably broken down, as evidenced by the defendant's notice of termination. The court held that damages would be an adequate remedy for the plaintiff in the event of wrongful termination, and it would not be appropriate to force the defendant to maintain the plaintiff at the work site or to supervise the construction works. However, the court recognized the plaintiff's legitimate concern to value the work done on site to support its claim in arbitration. Accordingly, the court declined to grant the broad interim injunctions sought but directed the defendant to permit and facilitate the plaintiff to conduct a valuation of...

Court Disposition

Application for interim injunctions largely declined; limited order granted for valuation of works.

Orders

  • The defendant shall permit and/or facilitate the plaintiff to conduct a valuation of its works done at the construction site so far.
  • The parties to agree on a suitable timeframe and terms thereof and in any event on or before 19th December 2019.