[2014] KEELC 67 (KLR)

[2014] KEELC 67 (KLR)

The court found that although the original sale agreement did not make time of the essence, the plaintiff's issuance of two demand letters after a five-year delay constituted valid notice, thereby making time of the essence. The defendant's failure to act on these notices and to take necessary steps to facilitate...

Source-derived case information.

Citation
[2014] KEELC 67 (KLR)
Parties
Plaintiff: Stephen Kibet Malakwen; Defendant: Benson Gateca Mbugua
Court
Environment and Land Court
Court Station
Environment and Land Court at Kitale
Jurisdiction
Kenya
Case Number
Land Case 75 of 2013
Procedural Posture
Land Case / Judgment
Outcome
Judgment for the plaintiff; specific performance granted.
Judges
EO Obaga
Legal Topics
Specific Performance, Sale of Land, Contractual Obligations, Delay in Completion, Notices and Time of Essence
Source Language
en
Land and Property Specific Performance Sale of Land Contractual Obligations Delay in Completion Notices and Time of Essence

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 5 Party arguments 2 Amounts and remedies 5
Sign in to unlock

Parties

Stephen Kibet Malakwen

Plaintiff

Benson Gateca Mbugua

Defendant

Procedural Posture

Land Case / Judgment

  1. 1 Whether the defendant breached the sale agreement by failing to facilitate sub-division and transfer of the sold portion to the plaintiff.
  2. 2 Whether time became of the essence in the contract after the plaintiff issued demand letters.
  3. 3 Whether the plaintiff is entitled to an order of specific performance of the sale agreement.

Ratio Decidendi

The court found that although the original sale agreement did not make time of the essence, the plaintiff's issuance of two demand letters after a five-year delay constituted valid notice, thereby making time of the essence. The defendant's failure to act on these notices and to take necessary steps to facilitate sub-division and transfer, despite full payment by the plaintiff and the plaintiff's possession and development of the land, amounted to an unreasonable delay and breach of contract. The defendant's claimed willingness to perform was not supported by evidence of actual steps taken. Accordingly, the plaintiff was entitled to an order of specific performance to compel the defendant...

Court Disposition

Judgment for the plaintiff; specific performance granted.

Orders

  • An order of specific performance of the agreement for sale dated 3/2/2009 is issued.
  • If the defendant does not comply, the Deputy Registrar is empowered to sign all documents necessary to give effect to the agreement.