[2016] KEELC 133 (KLR)

[2016] KEELC 133 (KLR)

The court found that the defendant breached the contract by excavating up to 8 metres below the river bed instead of the agreed 2 metres, as evidenced by the plaintiff's uncontroverted surveyor's report. The court held that the river was re-routed by the defendant's quarrying activities, creating a public hazard....

Source-derived case information.

Citation
[2016] KEELC 133 (KLR)
Parties
Plaintiff: Stephen Muriithi Mathenge; Defendant: S.S. Mehta & Sons Ltd
Court
Environment and Land Court
Court Station
Environment and Land Court at Nakuru
Jurisdiction
Kenya
Case Number
Environment & Land Case 372 of 2013
Procedural Posture
Civil Suit / Judgment
Outcome
Judgment for the plaintiff in part; orders for restoration and compensation granted.
Judges
MA Silau
Legal Topics
Land Extraction Contracts, Environmental Impact Assessment, Breach of Contract, Remedies for Land Damage
Source Language
en
Land and Property Environmental Law Land Extraction Contracts Environmental Impact Assessment Breach of Contract Remedies for Land Damage

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 1 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Stephen Muriithi Mathenge

Plaintiff

S.S. Mehta & Sons Ltd

Defendant

Procedural Posture

Civil Suit / Judgment

  1. 1 Whether the defendant breached the excavation contract by exceeding the agreed depth of 2 metres below the river bed.
  2. 2 Whether the defendant was obligated to restore the site, replant vegetation, or erect a fence after excavation.
  3. 3 Whether the defendant unlawfully re-routed the river and the appropriate remedy for such action.

Ratio Decidendi

The court found that the defendant breached the contract by excavating up to 8 metres below the river bed instead of the agreed 2 metres, as evidenced by the plaintiff's uncontroverted surveyor's report. The court held that the river was re-routed by the defendant's quarrying activities, creating a public hazard. However, the court found no contractual or statutory obligation on the defendant to replant vegetation or erect a fence, and no sufficient evidence of damage to trees or fences beyond the excavation area. The court ordered the defendant to back-fill the pit to restore it to the agreed 2-metre depth and to re-route the river to its original course under NEMA supervision. The...

Court Disposition

Judgment for the plaintiff in part; orders for restoration and compensation granted.

Orders

  • Defendant to back-fill the site up to a depth of 2 metres below the original river bed level within 90 days.
  • Defendant to re-route the river back to its original position before excavation within 90 days, under NEMA supervision.