[2012] KEELRC 226 (KLR)

[2012] KEELRC 226 (KLR)

The court found that the cause of action arose on 18-8-1999, the date the claimant's employment was terminated. Under Section 4(1) of the Limitation of Actions Act, the limitation period for contractual claims is six years. The claim was filed on 25-10-2010, more than eleven years after the cause of action arose,...

Source-derived case information.

Citation
[2012] KEELRC 226 (KLR)
Parties
Claimant: Stephen Ndungu Kariuki; Respondent: G4S Security Services Limited
Court
Employment and Labour Relations Court
Court Station
Employment and Labour Relations Court at Nairobi
Jurisdiction
Kenya
Case Number
Cause 1296 of 2010
Procedural Posture
Employment Claim / Ruling on Preliminary Objection
Outcome
claim struck out as time barred
Judges
AN Makau
Legal Topics
Limitation Periods, Employment Termination, Jurisdiction of Employment Court
Source Language
en
Employment and Labour Limitation Periods Employment Termination Jurisdiction of Employment Court

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 5 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Stephen Ndungu Kariuki

Claimant

G4S Security Services Limited

Respondent

Procedural Posture

Employment Claim / Ruling on Preliminary Objection

  1. 1 Whether the claim was filed out of time contrary to the Limitation of Actions Act.
  2. 2 Whether the claimant had capacity to sue after the limitation period had lapsed.

Ratio Decidendi

The court found that the cause of action arose on 18-8-1999, the date the claimant's employment was terminated. Under Section 4(1) of the Limitation of Actions Act, the limitation period for contractual claims is six years. The claim was filed on 25-10-2010, more than eleven years after the cause of action arose, and no leave of court was sought to file out of time. The Employment Act, 2007, which reduced the limitation period to three years, was not applicable as both the contract and cause of action predated its commencement. The court held that the claim was time barred and that the claimant's capacity to sue had lapsed. The claim was therefore struck out as an abuse of court process.

Court Disposition

claim struck out as time barred

Orders

  • The claim is struck out for being time barred.
  • No order as to costs.