Storm Hotel Limited v Kenya Power & Lighting Company Limited (Civil Appeal E008 of 2025) [2025] KEHC 18686 (KLR) (17 December 2025) (Judgment)

Storm Hotel Limited v Kenya Power & Lighting Company Limited (Civil Appeal E008 of 2025) [2025] KEHC 18686 (KLR) (17 December 2025) (Judgment)

The appeal was dismissed because the lower court was functus officio after judgment, the orders sought were moot, and no live controversy remained. The interlocutory orders had been spent upon delivery of judgment, and the court had no jurisdiction to revisit them.

Source-derived case information.

Citation
[2025] KEHC 18686 (KLR)
Parties
Appellant: Storm Hotel Limited; Respondent: Kenya Power & Lighting Co. Ltd
Court
High Court
Jurisdiction
Kenya
Case Number
Civil Appeal E008 of 2025
Procedural Posture
Civil Appeal / Judgment
Outcome
Appeal dismissed
Legal Topics
Functus Officio, Mootness Doctrine, Costs, Interlocutory Orders
Source Language
en
Civil Procedure Functus Officio Mootness Doctrine Costs Interlocutory Orders

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 11 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Storm Hotel Limited

Appellant

Kenya Power & Lighting Co. Ltd

Respondent

Procedural Posture

Civil Appeal / Judgment

  1. 1 Whether the lower court was functus officio in relation to the interlocutory orders after judgment
  2. 2 Whether the appeal raised any live controversy or was moot
  3. 3 Whether costs should be awarded and to what extent

Ratio Decidendi

The appeal was dismissed because the lower court was functus officio after judgment, the orders sought were moot, and no live controversy remained. The interlocutory orders had been spent upon delivery of judgment, and the court had no jurisdiction to revisit them.

Court Disposition

Appeal dismissed

Orders

  • The appeal is dismissed with costs of Ksh. 70,000 to the respondent.
  • 30 days stay of execution granted.