[2023] KEHC 21753 (KLR)

[2023] KEHC 21753 (KLR)

The court found that, although the appellant undertook additional works and incurred extra costs, it was aware that approval from the respondent's Board of Trustees was required for such variations. The appellant's own correspondence admitted that it overlooked the need to seek board approval for the additional...

Source-derived case information.

Citation
[2023] KEHC 21753 (KLR)
Parties
Appellant: Straight Media Limited; Respondent: The Trustees JKUAT Retirement Benefit Scheme
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Commercial Appeal E120 of 2022
Procedural Posture
Commercial Appeal / Judgment
Outcome
appeal dismissed
Judges
DAS Majanja
Legal Topics
Contractual Obligations, Breach of Contract, Agency Authority, Approval of Variations
Source Language
en
Commercial and Corporate Civil Procedure Contractual Obligations Breach of Contract Agency Authority Approval of Variations

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 3 Party arguments 2 Amounts and remedies 7
Sign in to unlock

Parties

Straight Media Limited

Appellant

The Trustees JKUAT Retirement Benefit Scheme

Respondent

Procedural Posture

Commercial Appeal / Judgment

  1. 1 Whether the appellant required approval from the respondent's Board of Trustees to incur additional costs and carry out expanded works.
  2. 2 Whether the respondent is estopped from denying authorization of additional works approved by its agents.
  3. 3 Whether the appellant is entitled to payment for additional works and expenses incurred without formal approval.

Ratio Decidendi

The court found that, although the appellant undertook additional works and incurred extra costs, it was aware that approval from the respondent's Board of Trustees was required for such variations. The appellant's own correspondence admitted that it overlooked the need to seek board approval for the additional works and expenses. The court held that, in the absence of such approval, the respondent was not contractually bound to pay for the extra works. The approval by the project architect and administrator, as agents, did not suffice because the appellant was aware of the limitation of their authority. Consequently, the appellant was not entitled to the reliefs sought, and the appeal...

Court Disposition

appeal dismissed

Orders

  • The appeal is dismissed.
  • No order as to costs.