[2017] KEHC 6710 (KLR)

[2017] KEHC 6710 (KLR)

The court found that section 67(a) of the Kenya Roads Act, 2007, imposes a mandatory requirement for a party to serve a written notice of at least 30 days on the Director General of the Kenya National Highways Authority before instituting legal proceedings. The plaintiff failed to comply with this requirement....

Source-derived case information.

Citation
[2017] KEHC 6710 (KLR)
Parties
Plaintiff: Sumac Development Company Limited; Defendant: George Munyui Kigathi; Defendant: Jennifer Ngina Kigathi; Defendant: Kenya National Highways Authority
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Case 348 of 2013
Procedural Posture
Civil Case / Ruling on Preliminary Objection
Outcome
preliminary objection allowed; suit against 3rd defendant struck out with costs
Judges
LM Njuguna
Legal Topics
Preliminary Objection, Statutory Notice Requirement, Limitation Periods, Road Reserve Land, Striking Out Suit
Source Language
en
Civil Procedure Land and Property Preliminary Objection Statutory Notice Requirement Limitation Periods Road Reserve Land Striking Out Suit

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 8 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Sumac Development Company Limited

Plaintiff

George Munyui Kigathi

Defendant

Jennifer Ngina Kigathi

Defendant

Kenya National Highways Authority

Defendant

Procedural Posture

Civil Case / Ruling on Preliminary Objection

  1. 1 Whether the plaintiff's suit against the 3rd defendant is incompetent for failure to serve a statutory notice under section 67(a) of the Kenya Roads Act, 2007.
  2. 2 Whether the suit is time-barred under section 67(b) of the Kenya Roads Act, 2007.

Ratio Decidendi

The court found that section 67(a) of the Kenya Roads Act, 2007, imposes a mandatory requirement for a party to serve a written notice of at least 30 days on the Director General of the Kenya National Highways Authority before instituting legal proceedings. The plaintiff failed to comply with this requirement. Furthermore, the cause of action against the 3rd defendant arose on 8th October, 2010, but the 3rd defendant was only enjoined in the proceedings by an amended plaint filed on 2nd June, 2015, well outside the statutory limitation period of twelve months prescribed by section 67(b). The court held that the constitutional arguments advanced by the plaintiff did not override the clear...

Court Disposition

preliminary objection allowed; suit against 3rd defendant struck out with costs

Orders

  • The plaintiff's suit against the 3rd defendant is struck out with costs.