[2025] KEHC 1749 (KLR)
The court found that the plaintiffs had fully complied with their obligations under the sale agreement by paying the entire purchase price and seeking possession of the apartment. The defendant failed to deliver possession and did not complete the apartment as required by the agreement. The agreement expressly...
Source-derived case information.
- Citation
- [2025] KEHC 1749 (KLR)
- Parties
- Plaintiff: Nizarali Pradhan Sumar; Plaintiff: Shehnaz Nizarali Sumar; Defendant: VK Construction Limited
- Court
- High Court
- Court Station
- High Court at Nairobi (Milimani Commercial Courts)
- Jurisdiction
- Kenya
- Case Number
- Civil Suit E351 of 2019
- Procedural Posture
- Civil Suit / Judgment
- Outcome
- Judgment for the plaintiffs as prayed in the plaint.
- Judges
- A Mabeya
- Legal Topics
- Breach of Contract, Sale of Land, Specific Performance, Refund of Purchase Price
- Source Language
- en
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Nizarali Pradhan Sumar
Plaintiff
Shehnaz Nizarali Sumar
Plaintiff
VK Construction Limited
Defendant
Procedural Posture
Civil Suit / Judgment
Legal Issues
- 1 Whether the defendant breached the sale agreement by failing to deliver possession of the apartment to the plaintiffs.
- 2 Whether the plaintiffs are entitled to repudiate the agreement and obtain a refund of the purchase price and related costs.
Ratio Decidendi
The court found that the plaintiffs had fully complied with their obligations under the sale agreement by paying the entire purchase price and seeking possession of the apartment. The defendant failed to deliver possession and did not complete the apartment as required by the agreement. The agreement expressly provided that, in such circumstances, the plaintiffs were entitled to rescind the contract and receive a refund of all monies paid. The defendant offered no justification for its failure and did not participate in the proceedings. The court concluded that the plaintiffs had proven their case on a balance of probabilities and were entitled to judgment as prayed, including a refund of...
Court Disposition
Judgment for the plaintiffs as prayed in the plaint.
Orders
- Declaration that the plaintiffs are entitled to repudiate the agreement of sale dated 23/4/2015.
- Declaration that the plaintiffs are entitled to a refund of the full purchase price of Kshs. 18,860,000/-.
Full Case Text
Judgment text and source record
33 paragraphs
Sumar & another v VK Construction Limited (Civil Suit E351 of 2019) [2025] KEHC 1749 (KLR) (Commercial and Tax) (25 February 2025) (Judgment)
Neutral citation: [2025] KEHC 1749 (KLR)
Republic of Kenya
In the High Court at Nairobi (Milimani Commercial Courts)
Commercial and Tax
Civil Suit E351 of 2019
A Mabeya, J
February 25, 2025
Between
Nizarali Pradhan Sumar
1st Plaintiff
Shehnaz Nizarali Sumar
2nd Plaintiff
and
VK Construction Limited
Defendant
Judgment
1. The plaintiffs instituted this suit against the defendant vide a plaint dated 20/9/2019. They sought judgment against the defendant for a declaration that the plaintiff was entitled to repudiate the agreement of sale dated 23/4/2015. The plaintiffs further sought for a declaration that they are entitled to the full purchase price of Kshs. 28,860,000/- with interest, Kshs. 549,490/- plus interest and for loss of income at the rate of Kshs. 150,000/- per month. The plaintiff further prayed for costs of the suit together with interest at court rates.
2. The plaintiffs case was that the defendant had developed the suit property by erecting 32 four bedroom apartments. The plaintiffs entered into a sale agreement dated 23/4/2015 for the purchase of apartment 804. It was a term of the agreement that the defendant would expedite the construction of the estate and the completion date would be 15 days after receipt of the architect’s certificate of completion.
3. The plaintiffs stated that the parties had agreed that the purchase price was Kshs. 18,800,000/- payable in installments. That upon signing of the agreement, the parties agreed to a variation of the apartment from a four-bedroom apartment to a three-bedroom apartment. That the plaintiffs made payments amounting to Kshs. 18,860,000/- made plans to inspect the apartment.
4. On inspection, they realized that there were several defects and incomplete works which were not attended to. The plaintiffs incurred a cost of Kshs. 489,490/- for finishing the suit properties. It was stated that the defendant authorized agents had refused to give the plaintiffs access or possession of the apartment and when they finally did, it was not in a habitable condition.
5. The defendant did not enter appearance or file any defence. The matter proceeded to formal proof on 26/5/2021.
6. PW1 Nizarali Pradhan Sumar relied on his witness statement and produced the bundle of documents as exhibit. He testified that he paid the whole purchase price of Kshs. 18,860,000/- but had not been able to take possession of the property. That there was water leakage for every bedroom and the finishing was not well done as the defendant did a shoddy job which was covered up with cement. That a completion notice was issued to the defendant but it failed to respond to it.
7. The plaintiff filed submissions dated 2/11/2021. The plaintiff submitted that the defendant breached the terms of the agreement by failing to deliver possession of the apartment and grant the plaintiffs access contrary to clause 2 of the agreement.
8. Counsel submitted that pursuant to clause 11 of the agreement, the plaintiffs were entitled to rescind the agreement and the defendant was duly served with the completion notice. It was the plaintiffs’ submission that they were entitled to a refund of the purchase price and the cost incurred for valuation as well as the price for fixtures.
9. Having considered the pleadings and submissions on record, the main issue for determination is whether judgment should be entered against the defendant as sought in the plaint. The plaintiffs have approached the court seeking a refund of the purchase price for apartment number 804, which was paid in accordance with the agreement between the parties dated 23/4/2015.
10. The plaintiffs assert that the defendant breached the agreement by failing to grant them possession of the apartment and by not completing the construction within the agreed timelines.
11. Upon reviewing the agreement, it is evident that clause one imposed an obligation on the defendant to ensure the construction of the 32 flats was carried out expeditiously. The agreement also outlined the mode of payment, which the plaintiffs duly adhered to. Regarding completion, the agreement stipulated that the project would be considered complete either 15 days after the vendor’s architect issued a certificate confirming the completion of the development or by 30/4/2015, whichever was later.
12. Since the plaintiffs fulfilled their contractual obligations, the defendant was equally bound to honor its commitments. By failing to do so, the defendant was in clear breach of the agreement. No justifiable reason has been provided to explain the defendant’s refusal to allow the plaintiffs to take possession of the apartment.
13. Furthermore, as per clause 11 of the agreement, upon failure to complete the development and hand over possession, the defendant was obligated to compensate the plaintiffs by refunding all monies paid toward the purchase price.
14. Based on the foregoing, I find that the plaintiffs have sufficiently proven their case against the defendant and are entitled to the reliefs sought. Accordingly, I enter judgment in favor of the plaintiffs as prayed for in the plaint.
It is so decreed.
SIGNED AT KISUMU THIS 17TH DAY OF FEBRUARY, 2025. A. MABEYA, FCI ARBJUDGEDATED AND DELIVERED AT NAIROBI THIS 25TH DAY OF FEBRUARY, 2025. F. GIKONYOJUDGE