[2018] KECA 548 (KLR)

[2018] KECA 548 (KLR)

The Court of Appeal found that the respondent had not substantially completed the construction works as required by the contract, as significant elements such as servant quarters, drainage, driveway, and car parks were not completed in accordance with the drawings and specifications. The trial judge erred in relying...

Source-derived case information.

Citation
[2018] KECA 548 (KLR)
Parties
Appellant: Sun Sand Dunes Limited; Respondent: Raiya Construction Limited
Court
Court of Appeal
Court Station
Court of Appeal at Malindi
Jurisdiction
Kenya
Case Number
Civil Appeal 26 of 2017
Procedural Posture
Civil Appeal / Judgment on Appeal
Outcome
appeal allowed; trial court judgment set aside; respondent's claim dismissed; appellant's counter-claim partially allowed
Judges
ARM Visram, J Karanja, FI Koome
Legal Topics
Construction Contracts, Breach of Contract, Remedies for Breach, Expert Evidence, Contractual Penalties
Source Language
en
Commercial and Corporate Civil Procedure Construction Contracts Breach of Contract Remedies for Breach Expert Evidence Contractual Penalties

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 5 Authorities cited 12 Party arguments 2 Amounts and remedies 6
Sign in to unlock

Parties

Sun Sand Dunes Limited

Appellant

Raiya Construction Limited

Respondent

Procedural Posture

Civil Appeal / Judgment on Appeal

  1. 1 Whether the respondent substantially completed the construction works as per the contract terms.
  2. 2 Whether the appellant was justified in withholding payment and refusing to take possession of the premises.
  3. 3 Whether the respondent was entitled to additional payments and security costs.

Ratio Decidendi

The Court of Appeal found that the respondent had not substantially completed the construction works as required by the contract, as significant elements such as servant quarters, drainage, driveway, and car parks were not completed in accordance with the drawings and specifications. The trial judge erred in relying heavily on expert evidence that was compromised and failed to account for uncompleted works. The appellant was justified in withholding further payments, having already paid three-quarters of the contract sum, and was not in breach. The respondent was not entitled to additional sums for materials or security costs, as these were not contractually agreed. The penalty clause for...

Court Disposition

appeal allowed; trial court judgment set aside; respondent's claim dismissed; appellant's counter-claim partially allowed

Orders

  • A declaration is issued that the respondent breached the contract dated 4th November, 2008.
  • A mandatory injunction is issued directing the respondent to unconditionally hand over the suit premises to the appellant.