The court found that there was a valid contract between the parties for the construction of a car park, as evidenced by the Bill of Quantities and the conduct of both parties. The respondent performed the work to the satisfaction of the appellant, who made partial payments but failed to pay the full contractual sum....

Source-derived case information.

Citation
[2019] KEHC 4413 (KLR)
Parties
Appellant: Taidy’s Restaurant; Respondent: Gerfas Otieno Sammy t/a Nyanco Investment Contractors
Court
High Court
Court Station
High Court at Kericho
Jurisdiction
Kenya
Case Number
Civil Appeal 16 of 2015
Procedural Posture
Civil Appeal / Judgment
Outcome
appeal dismissed
Judges
EM Ngugi, GMA Dulu
Legal Topics
Oral Contracts, Burden of Proof, Construction Contracts, Quantum Meruit
Source Language
en
Commercial and Corporate Civil Procedure Oral Contracts Burden of Proof Construction Contracts Quantum Meruit

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 2 Authorities cited 5 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Taidy’s Restaurant

Appellant

Gerfas Otieno Sammy t/a Nyanco Investment Contractors

Respondent

Procedural Posture

Civil Appeal / Judgment

  1. 1 Whether there was a valid and enforceable contract between the parties for the construction work performed by the respondent.
  2. 2 Whether the respondent proved his claim for the outstanding contractual sum on a balance of probabilities.
  3. 3 Whether the trial court erred in relying on the Bill of Quantities as evidence of the contract and the amount due.

Ratio Decidendi

The court found that there was a valid contract between the parties for the construction of a car park, as evidenced by the Bill of Quantities and the conduct of both parties. The respondent performed the work to the satisfaction of the appellant, who made partial payments but failed to pay the full contractual sum. The appellant's shifting positions regarding the respondent's status and the value of work undermined its credibility. The trial court correctly applied the law on oral contracts and the burden of proof, finding that the respondent had proved his case on a balance of probabilities. The appeal lacked merit and was dismissed, affirming the trial court's judgment in favour of the...

Court Disposition

appeal dismissed

Orders

  • The appeal is dismissed with costs to the respondent.