[2025] KEHC 6842 (KLR)

[2025] KEHC 6842 (KLR)

The court found that although the respondent claimed the contract had already been signed with another contractor and the project handed over, there was no conclusive proof of handover or commencement of works. The dispute between the parties is under arbitration, and the value of works already completed by the...

Source-derived case information.

Citation
[2025] KEHC 6842 (KLR)
Parties
Applicant: Terracraft (K) Ltd; Respondent: County Government Of Tharaka Nithi
Court
High Court
Court Station
High Court at Nairobi (Milimani Commercial Courts)
Jurisdiction
Kenya
Case Number
Civil Suit E216 of 2025
Procedural Posture
Civil Suit / Ruling on Interim Measures of Protection
Outcome
Interim measures of protection granted in part; valuation of applicant's works ordered; stay of execution of new contract and commencement of works until valuation is completed.
Judges
F Gikonyo
Legal Topics
Interim Measures, Arbitration Proceedings, Public Procurement, Contract Termination
Source Language
en
Commercial and Corporate Civil Procedure Interim Measures Arbitration Proceedings Public Procurement Contract Termination

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 7 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Terracraft (K) Ltd

Applicant

County Government Of Tharaka Nithi

Respondent

Procedural Posture

Civil Suit / Ruling on Interim Measures of Protection

  1. 1 Is the applicant entitled to interim measures of protection pending the hearing and determination of its motion dated 20th March 2025?
  2. 2 Should the respondent be restrained from concluding the tendering process, awarding the contract to a different contractor, or removing the applicant from the construction site pending arbitration?
  3. 3 Has the subject matter of the arbitration been overtaken by events, and what is the appropriate relief?

Ratio Decidendi

The court found that although the respondent claimed the contract had already been signed with another contractor and the project handed over, there was no conclusive proof of handover or commencement of works. The dispute between the parties is under arbitration, and the value of works already completed by the applicant remains at risk. The court determined that interim measures are warranted to preserve the subject matter of the arbitration and prevent irreparable loss. Accordingly, the court ordered a valuation of the applicant's works, required the respondent to facilitate access for this purpose, and stayed execution of the new contract and commencement of works until the valuation...

Court Disposition

Interim measures of protection granted in part; valuation of applicant's works ordered; stay of execution of new contract and commencement of works until valuation is completed.

Orders

  • The applicant shall conduct a valuation of its works done at the construction site so far.
  • The respondent shall permit entry and facilitate the applicant to conduct the valuation of its works done at the construction site so far.