[2020] KEHC 7474 (KLR)

[2020] KEHC 7474 (KLR)

The court found that the appellant was only entitled to payment for work certified by the project manager, as evidenced by the interim certificate for Kshs 340,924. There was no evidence of completion or further certification for additional sums. The contract expressly provided for compensation in the form of...

Source-derived case information.

Citation
[2020] KEHC 7474 (KLR)
Parties
Appellant: Thomas Mboya Odera T/A Nyanza Trowellers; Respondent: County Government of Kisumu; Respondent: City Manager- City of Kisumu; Respondent: Kisumu City Management Board
Court
High Court
Court Station
High Court at Kisumu
Jurisdiction
Kenya
Case Number
Civil Appeal 48 of 2018
Procedural Posture
Civil Appeal / Judgment
Outcome
appeal dismissed
Legal Topics
Breach of Contract, Contractual Damages, Interest on Judgment Debt, Construction Contracts
Source Language
en
Commercial and Corporate Civil Procedure Breach of Contract Contractual Damages Interest on Judgment Debt Construction Contracts

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 3 Authorities cited 2 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Thomas Mboya Odera T/A Nyanza Trowellers

Appellant

County Government of Kisumu

Respondent

City Manager- City of Kisumu

Respondent

Kisumu City Management Board

Respondent

Procedural Posture

Civil Appeal / Judgment

  1. 1 Whether the trial court erred in failing to award general damages for breach of contract.
  2. 2 Whether the appellant was entitled to payment beyond the certified interim certificate amount.
  3. 3 Whether the appellant proved his claim for additional sums and general damages on a balance of probabilities.

Ratio Decidendi

The court found that the appellant was only entitled to payment for work certified by the project manager, as evidenced by the interim certificate for Kshs 340,924. There was no evidence of completion or further certification for additional sums. The contract expressly provided for compensation in the form of interest for delayed payments, and the appellant failed to provide evidence of the applicable interest rate. The claim for general damages was rejected as general damages are not awardable for breach of contract, in line with binding precedent. The appellant also failed to prove that his alleged losses were directly attributable to the respondent's actions. Consequently, the appeal...

Court Disposition

appeal dismissed

Orders

  • The appeal is dismissed with costs to the respondents.