[2023] KEELC 18975 (KLR)

[2023] KEELC 18975 (KLR)

The court found that the plaintiff was entitled to interest on the compensation award for the 251-day delay between the award and payment, as the Land Acquisition Act (repealed) mandated interest where possession was taken before full payment. The court also held that the plaintiff was entitled to compensation for...

Source-derived case information.

Citation
[2023] KEELC 18975 (KLR)
Parties
Plaintiff: Tonini Holdings Limited; Defendant: Kenya Urban Roads Authority; Defendant: The National Land Commission
Court
Environment and Land Court
Court Station
Environment and Land Court at Nairobi
Jurisdiction
Kenya
Case Number
Environment & Land Case 005 of 2022
Procedural Posture
Environment and Land Case / Judgment
Outcome
Judgment for the plaintiff in part; interest and professional costs awarded; each party to bear own costs.
Judges
JA Mogeni
Legal Topics
Compulsory Acquisition, Compensation Assessment, Interest on Awards, Valuation of Improvements, Public Purpose Acquisition
Source Language
en
Land and Property Civil Procedure Compulsory Acquisition Compensation Assessment Interest on Awards Valuation of Improvements Public Purpose Acquisition

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 4 Authorities cited 11 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Tonini Holdings Limited

Plaintiff

Kenya Urban Roads Authority

Defendant

The National Land Commission

Defendant

Procedural Posture

Environment and Land Case / Judgment

  1. 1 Whether the plaintiff is entitled to interest for delayed compensation following compulsory acquisition of land.
  2. 2 Whether the plaintiff is entitled to additional compensation for professional fees and costs incurred in preparation for development on the acquired land.
  3. 3 Whether the compensation award complied with the principles and statutory requirements for compulsory acquisition.

Ratio Decidendi

The court found that the plaintiff was entitled to interest on the compensation award for the 251-day delay between the award and payment, as the Land Acquisition Act (repealed) mandated interest where possession was taken before full payment. The court also held that the plaintiff was entitled to compensation for professional fees and costs incurred in preparation for the development of hostels, as these expenses were reasonably attributable to the compulsory acquisition and supported by evidence. The court rejected the defendants' argument that such claims should have been raised only at the inquiry stage, noting that the statutory framework and case law required fair compensation for...

Court Disposition

Judgment for the plaintiff in part; interest and professional costs awarded; each party to bear own costs.

Orders

  • Plaintiff awarded Kshs 4,610,064 as interest for delayed compensation.
  • Plaintiff awarded Kshs 105,463,367 for professional and construction costs incurred in preparation for development.